22 

FP8K-B / FP8K-DX / FP8K-DX-XLT 

Jun 2017-A 

 

LATCH & CABLE INSPECTION / ADJUSTMENTS  

 

WARNING!! Failure to perform routine inspections can lead to reduced service life, which could result 
in property damage and/or personal injury. Check locking latches for proper operation.  Inspect for 
worn or missing parts. Replace worn or damaged parts and adjust as required.

 

 

Ø

 

Latch Mechanism Inspection 

 

Latches and Latch Bar Alignment: 

§

  Check for proper latch operation on all four corners. 

§

  Observe locking latches during lift operation to ensure that all latches line up with slots in 

latch bar located in all four columns. If not, relocate and/or re-shim columns. 

§

  Check slack cable devices for proper operation.  Inspect for worn or missing parts. Replace 

worn or damaged parts as required. 

§

  Observe both locking latches and slack cable devices during lift operation to ensure that all 

latches line up with slots in latch bar located in all four columns. 

 

Ø

 

Leveling – Cable & Lock Ladder Adjustments 

 

A.  Initial Adjustment 

§

  Adjust cable with lift fully lowered.  Loosen jam nut and tighten nut on cable stud on top of 

column until yoke end is raised 1/4

” (6.4 mm) and back off nut one turn. Retighten jam nut. 

§

  Repeat for all four cables. 

 

B.  Final Adjustment 

1.  Load a typical vehicle on lift. 
2.  Raise lift as high as it will travel (full height). You should hear the locking latches click 

through all latch slots simultaneously. 

3.  Lower lift onto top latch position. 
4.  Check clearance, starting with the right front column, use a straight edge to mark the 

position of the yoke bottom on the column. 

5.  Raise lift to full height again. Mark second position. If gap between two marks is less than 

2

”, adjust locking latch bar to reach clearance of 2”. Repeat for the other three columns. 

6.  Adjust locking latch bar adjusting nut so that the bottom of the topmost latch bar slot is at 

least 2

” below locking latch.  After adjustment, tighten jam nut underneath column top plate,  

7.  If entire 2

” clearance cannot be attained by adjusting the locking latch bar, adjust the cable. 

Turn cable adjusting nut to raise the locking latch 2

” above bottom of latch bar slot. Tighten 

cable jam nut. 

8.  Lower lift and remove vehicle. 
9.  Raise the lift to full height. LISTEN and WATCH as the first locking latch clicks into place. 

Synchronize the other three columns with this column by adjusting their cables so all four 
latches click at same time. Tighten jam nuts. 

 

NOTE:  When making changes to adjustment nuts on cable end or latch bar stud, always leave at least 
two threads showing between nut and stud end.  Latches may not click in at the same time when 
vehicle is being raised but should be close.  Be sure all four corners have passed the locking latch bar 
slot before lowering lift on locking latches. 

 

 

 

 

 

 

Содержание FP8K-B

Страница 1: ...Jun 2017 A FP8K B FP8K DX FP8K DX XLT Four Post Storage Lifts 8 000 lbs Capacity 4 000 lbs per axle INSTALLATION OWNERS MANUAL...

Страница 2: ...ators read this manual 5 IMPORTANT Are you installing in a level location Lift must be anchored in place if slope is greater than 1 8 per foot 6 Make sure you have enough room to install the lock rods...

Страница 3: ...Column Height 86 94 Clearance between Columns 94 4 100 3 Clearance between Runways 37 2 42 2 Outside Runway to Outside Runway 74 8 80 7 Clearance Under Runways 70 78 Drive Thru Width 80 87 2 Locking P...

Страница 4: ...4 FP8K B FP8K DX FP8K DX XLT Jun 2017 A FP8K DX FP8K DX XLT FP8K DX FP8K DX FP8K DX XLT FP8K DX XLT 80 00 FP8K DX 87 20 FP8K DX XLT...

Страница 5: ...oper installation and level lifting If a floor is of questionable slope consider a survey of the site and or the possibility of pouring a new level concrete slab This lift is designed to be installed...

Страница 6: ...ster Kit Drip Trays Jack Tray OPTIONAL ACCESSORIES NOT SHOWN SJ 35 Sliding Scissor Jack 3 500 lbs capacity Aluminum Drive On Ramps 90 Degree Power Unit Bracket Kit only to the rear of Mainside Column...

Страница 7: ...Hose Jack Tray Lock Ladders and Hardware Box 2 While the Mainside Runway Fig 2 is upside down find the end of the Hydraulic Hose that is already connected to the Cylinder Locate hole on the side of t...

Страница 8: ...eviously chosen corner for the Power Unit 7 Unbolt all four Columns from the shipping brackets and place the Power Unit Column 1 with mount bracket in the above chosen corner Arrange the other three S...

Страница 9: ...Blocks 56 inside each column After removing the top Nut from the Lock Ladder you are ready to install the Top Caps A B 3 4 on the columns 12 Be aware of the offset hole in column s Top Caps Arrange To...

Страница 10: ...in 1 2 Note The variance will help in mounting the Runways later 15 Carefully lift and position each Runway into place and secure to Crossbeams ends with the provided Hex Bolts 44 Mounting Plate 42 an...

Страница 11: ...ensuring that the Crossbeam s Cable Pulley is between the Cable and the Lock Ladder as shown in Fig 6 This will allow the secondary Slack Cable Lock to function properly See Fig 6 below for Cable rou...

Страница 12: ...assists in keeping the Cables properly engaged to the Pulleys Fig 8 20 Install Lock Rods Linkage components per the drawing Fig 9 below Ensure to install Eye bolts 69 to outside middle of each Crossbe...

Страница 13: ...ulic Hose 89 to the Fitting on the side of the Main side Runway and attach the other end to the 90 degree Fitting on the Power Unit as shown in Fig 10 Fig 10 24 Now raise the complete unit Lift and se...

Страница 14: ...hen adjusting the Nylon Nut Make sure that threads engage through the nylon on each Nylon Nut 28 Install the Plastic drip Boards 51A into the bracket slots on the underside of the Mainside Runway as s...

Страница 15: ...ails 4 Install the four Pivot Pins 106 and Hairpin Cotter Pins 105 to secure Caster assembly to each crossbeam 5 Lower the Lift confirming that the Caster assemblies engage the columns and all four Co...

Страница 16: ...talling lifts and anchors typically 2 to 3 weeks ANCHORING TIPS 1 Use a concrete hammer drill with a carbide tip solid drill bit the same diameter as the anchor 3 4 775 to 787 inches diameter Do not u...

Страница 17: ...ibed in this manual Use only manufacturer s recommended attachments ALWAYS WEAR SAFETY GLASSES Everyday eyeglasses only have impact resistant lenses they are not safety glasses SAFETY PROCEDURES Never...

Страница 18: ...re vehicle is neither front nor rear heavy Raising Lift Push up switch to raise lift until platform runways clear floor Stop and check for vehicle movement and vehicle weight distribution If secure ra...

Страница 19: ...isually while in operation Check safety latches for free movement and full engagement with rack Check hydraulic connections and hoses for leakage Check cables connections for bends cracks and proper t...

Страница 20: ...oo quickly while under a heavy load Lower the lift slowly under heavy loads Motor Hums and Will Not Run 1 Lift overloaded Remove excessive weight from lift WARNING The voltages used in the lift can ca...

Страница 21: ...21 FP8K B FP8K DX FP8K DX XLT Jun 2017 A POWER UNIT PRIMING PROCEDURE WARNING Failure to properly relieve pressure in the following steps can cause injury to personnel...

Страница 22: ...s high as it will travel full height You should hear the locking latches click through all latch slots simultaneously 3 Lower lift onto top latch position 4 Check clearance starting with the right fro...

Страница 23: ...23 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 1...

Страница 24: ...24 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 2...

Страница 25: ...25 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 3...

Страница 26: ...26 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 4 41...

Страница 27: ...27 FP8K B FP8K DX FP8K DX XLT Jun 2017 A EXPLODED VIEW 5...

Страница 28: ...XLT 020 TT7B 200 11NEW Sheave Shaft GZ Crossbeam 4 21 FP8K DS DX XLT 021 TT7B 200 08 Cable Sheave 10 21A FP8K DS DX XLT 021A GB70 1 2000 M8 40 Cable Guide Bolt Crossbeam M8x40 4 21B FP8K DS DX XLT 02...

Страница 29: ...sher D6 6 53C FP8K DS DX XLT 053C TT 8136J 500 01 Ramp Yellow Caution metal Strip DX 2 54 FP8K DS DX XLT 054 GB91 Cotter Pin D5x60 2 55 FP8K DS DX XLT 055 DPF4 3 2 500 02 Cylinder Pin 1 56 FP7K 8K 403...

Страница 30: ...05 Elbow Fitting Power Unit 1 91 FP8K DS DX XLT 091 TPF4 500 09 Hex Nut Power Unit 2 92 FP8K DS DX XLT 092 TPF4 500 08 Washer Power Unit 2 93 FP8K DS DX XLT 093 TPF4 500 07 Fitting Power Unit 1 94 FP...

Страница 31: ...Offside Runway DS DX XLT 1 56 FP7K 8K 4047 HYDRAULIC CYLINDER FP7K 8K DS DX XLT 1 61 FP8K DS DX XLT JT DPF4 3 2 600 00T Jack Tool Tray 42 x12 DS DX XLT 1 67 FP8K DS DX XLT 067 TT 8138 200 01 00 Crossb...

Страница 32: ...age is not considered a warranty issue and therefore must be noted for any potential recovery with the shipping company The customer is required to notify Tuxedo of any missing parts within 72 hours T...