37
mWing
Installation and mounting
7.3
Steps to be taken
The following work step must be carried out prior to mounting:
›
Build foundation and lay empty conduits.
The following work steps must be carried out during mounting:
›
Unpack the pedestrian gate.
›
Align the pedestrian gate.
›
Prepare the pedestrian gate for mounting and electrical connection.
›
Mount the pedestrian gate.
›
Connect the pedestrian gate electrically.
›
Assemble the pedestrian gate.
7.4
Building foundation and laying empty conduits
7.4.1
Requirements foundation
The foundation must meet the following requirements:
›
Have sufficient load-carrying capacity.
›
Concrete C20/25 or corresponding industrial floor
›
Fastening must have a secure grip
›
Foundation cross-section according to foundation and empty conduit plan
›
Non-slip surface
›
Horizontal and level.
Foundation and empty conduit plan:
When installing outdoors, the foundation must meet the following additional
requirements:
›
Concrete C35/45 XD 3 XF2
›
Foundation depth: at least
31.5" (
800 mm
)
, frost-proof. Adapt the
foundation
depth to the local conditions.
›
Reinforcement mesh according to reinforcement plan
Reinforcement plan: