Gravel specification 

Primary backfill specification: 

 

Primary backfill material should be free-flowing granular material. 

 

Compaction should be by lightweight rollers or vibratory plate. Compact gravel evenly to 
ensure proper support for the tank. Ensure the vibrating machine does not come in contact 
with the shell of the tank. 

 

Install  tanks  with  primary  backfill  only  within  the  region  immediately surrounding  the 
tanks. This primary backfill must extend a minimum of 250mm outward from the tank, and 
directly beneath the tank.  

 

Backfill material shall not  be frozen or  contain lumps of frozen material at any time during 
installation. 

 

Use of other than specified backfill and bedding materials will void the tank warranty. 
 

The following approved material is suitable for primary backfill: 

Rounded pea gravel: 

 

Minimum particle size 3mm, maximum 18 mm, compacted to a relative density of >70%.  

 

Gravel  shall  be  clean  and  free  flowing,  free  from  large  rocks,  dirt,  sand,  roots,  organic 
materials or debris.  

 

Upon  screening  analysis,  the  backfill  material  shall  have  no  more  than  5%  by  weight 
passing 2.36 mm sieve. 

or 

 

Crushed or processed stone: 

 

Minimum particle size 3 mm, maximum 12 mm, compacted to a relative density of >40% 

 

Dry Gravel density must be at least 1500 kg/m3. The material should be washed or screened to 
remove fine particles.  

 

Upon screening analysis, the backfill material shall have no more than 5% by weight passing 
2.36 mm sieve. 

 

Pea Gravel 

 

 

Crushed Stone 

 

 

Содержание Novo UK10

Страница 1: ...0 106 Rev 11 Dec 2017 Tricel Novo UK6 50 Wastewater Treatment Plants Engineering a green future...

Страница 2: ...6 6m 14 5 Installation 15 5 1 Installation planning 15 5 2 Inspection opon reception of tanks 15 5 3 Positioning and precautions 15 5 4 Types of installation 16 5 5 Installation procedure 17 5 5 1 Exc...

Страница 3: ...nance 32 8 1 Regular maintenance 32 8 2 Annual maintenance 32 8 3 Annual service availablefromyoursupplier 32 8 4 Production of sludge 33 8 5 De sludging emptying the solid waste from the primary cham...

Страница 4: ...3...

Страница 5: ...4...

Страница 6: ...hing and protective equipment after working with sewage treatment plants Wash hands and face before eating drinking or smoking All manhole access covers must be kept locked for safety reasons Tanks ar...

Страница 7: ...olids float to the top of the water to create a scum The top layer acts as a seal and stops odours escaping This chamber separates up to 70 of the solids present 3 Next is the aeration chamber where m...

Страница 8: ...0 215 215 215 86 De sludge period minimum year 1 3 1 3 1 3 1 3 0 5 2 0 5 2 0 4 1 Thickness minimum mm 5 5 5 5 5 5 5 Retention time hours 83 78 76 74 64 59 56 Tanks may require a stepped foundation wit...

Страница 9: ...8 3 2 Tank drawings The arrow indicates a compartment which it is necessary to empty when de sludging the plant...

Страница 10: ...9...

Страница 11: ...10...

Страница 12: ...valve installed on the pumped outlet will prevent backflow into the plant Outlined below is the standard pump specification Other pump options are available to customer specifications if required ple...

Страница 13: ...compression fitting which is positioned on the turret of the Tricel Novo 50mm OD MDPE black piping must be connected to this end connector compression fitting to transfer the treated wastewater to the...

Страница 14: ...cations shown below It is best tolift tanks by a machine and webbing lifting straps do not use chains or wire ropes in contact with the tank Ensure tank is empty when lifting Care is needed to control...

Страница 15: ...cted per Option 3 shown below However on sites where lifting height is restricted a lifting bar should be used as shown in Option 4 Note To ensure the angle of the sling is not greater than 60o as per...

Страница 16: ...slope upstream o Are static or rolling loads present on this site Only suitably qualified personnel should install the Tricel Novo Suitably sized equipment will be required to excavate the hole and t...

Страница 17: ...l not rise higher than the invert of the inlet Sites where a higher water level is present ensure that the installation is suitable for the site conditions Tricel strongly advises the installation of...

Страница 18: ...t plantby a minimum 500mm to maintain a minimum space of 250mm all around the tank Note In gravel installations it is imperative that the gravel backfill is thoroughly compacted to maximise support fo...

Страница 19: ...by a qualified individual The Tricel Novo is not suitable where a deeper installation is required Outlined below are the minimum distances mm that the excavation dimensions must exceed the tank dimens...

Страница 20: ...el on the base 7 Connect and seal the pipe work to the tank Backfilling around the tank 8 Ballast the plant by filling each chamber with clean water to a depth of 300mm and recheck the pipe work level...

Страница 21: ...nstallation Use of other than specified backfill and bedding materials will void the tank warranty The following approved material is suitable for primary backfill Rounded pea gravel Minimum particle...

Страница 22: ...ete Where necessary this may be extended to include internal light vibration Never use deep reverberation which will substantially increase the pressure on the tank possibly causing failure Impact of...

Страница 23: ...site conditions 500mm requires a concrete backfill 750mm requires a concrete backfill 500mm or 750mm risers cannot be retrofitted unless the correct installation is in place TheTricel Novo is suitabl...

Страница 24: ...ing with concrete or gravel can commence 5 10 2 Sloping ground When the slope of the ground is 5 or more it is recommended to install a retaining wall to protect the tank from the lateral thrust Concr...

Страница 25: ...the responsibility of a qualified electrician Note In typical domestic installations asinglerunof1 5mm threecore twoconductorsplus earth conductor steel wire armoured SWA cable is required from the cu...

Страница 26: ...25 5 11 1 Electrical Diagrams 5 11 1 1 Tricel Novo Gravity Outlet UK6 UK8 UK10 UK12 Control Panel No 209102...

Страница 27: ...26 UK18 UK24 Control Panel No 209116...

Страница 28: ...27 UK30 UK36 UK42 UK50 Control Panel No 209111...

Страница 29: ...28 5 11 1 2 Tricel Novo Pumped Outlet UK6 UK8 UK10 UK12 UK18 UK24 Control Panel No 209101...

Страница 30: ...29 UK30 UK36 UK42 UK50 Control Panel No 209112...

Страница 31: ...ater during installation If you have not it should be filled before its first use If the plant is running correctly you will hear a slight hum from the air blower and there will be air bubbles coming...

Страница 32: ...and subsequent services in order to distribute the air evenly among the diffusers Warning Each valve must not be closed more than 50 as this will result in irreparable damage to the air blower Only T...

Страница 33: ...ity of the homeowner 8 1 Regular maintenance The vent around the base of the blower housing guarantees a fresh supply of air to the air blower All vents should be checked to make sure they are not blo...

Страница 34: ...sludge is 700mm deep For de sludging periods which depends on the occupancy of the dwelling please refer to the table in section 3 1 Dimensions Carry out de sludging with a vacuum tanker Tricel recom...

Страница 35: ...which is the responsibility of the homeowner If the plant installation is carried out incorrectly flooding overloading electrical shock or floatation might occur Tricel is not responsible for incorre...

Страница 36: ...here possible unnecessary human traffic around the plant should be avoided The Tricel Novo is only suitable for human faeces No animal faeces must enter the plant 10 Troubleshooting Properly installed...

Страница 37: ...alified person Blowers runs intermittently Thermal overload tripped Protect installation from the sun Air supply vent blocked clean if necessary Filter blocked replace if necessary Discharge hose bloc...

Страница 38: ...the level of liquid in the tank Ensure the pipes are not blocked and are fitted correctly to the tank Chemical kill of bacteria Ensure pumps are working properly If applicable If the symptom persists...

Страница 39: ...ctivated Sludge Shape Horizontal Cylinder with domed ends 620mm x 620mm and 200mm Access openings as required 4 Intended for Use To treat domestic wastewater for up to 50 population equivalent 5 Name...

Страница 40: ...d and hydraulic daily load of 0 9m 3 d Determined at temperatures 12 0 Material Performance Essential Characteristic Method Performance Harmonised Technical Specification Water Tightness Vacuum Test...

Страница 41: ...bwassertechnik GmbH Hergenrather Weg 30 52074 Aachen Number NB 1739 Treatment capacity Nominal organic daily load BOD5 Nominal Hydraulic daily flow QN As Set Out in Table CE for each Model Effectivene...

Страница 42: ...41 12 Terms conditions Subject to our standard terms and conditions which are available on request...

Страница 43: ...42...

Страница 44: ...is Tricel Novo is a Nominal Organic Daily Load BOD5 Kg Nominal Hydraulic Daily Flow Litres UK6 0 36 900 UK8 0 48 1200 UK10 0 6 1500 UK12 0 72 1800 UK18 1 08 2700 UK24 1 44 3600 UK30 1 8 4500 UK36 2 16...

Отзывы: