RLC-SVX19J_SHORT-GB
9
Installation Requirements
Elastomeric Isolators Installation
(Optional)
Isolators are ready to install. Mountings have to
be placed on a rigid and level foundation. External
equipment should not transmit additional vibration to
the chiller. The position of elastomeric isolator and
weight per point are given in the Neoprene isolators
installation drawing which is supplied with the chiller.
Wrong placement along the unit may result in excessive
defl ection.
1.
Secure the isolators to the mounting surface
using the mounting slots in the isolator’s base
plate. Do NOT fully tighten the isolators mounting
bolts at this time. See the isolators submittals for
isolators location, maximum weights, and isolators
diagrams.
2. Align the mounting holes in the base of the unit
with the threaded positioning pins on the top of the
isolators.
3. Install the unit on the isolators and secure the
isolators to the unit with a nut. The maximum
isolators defl ection should be 13 mm.
4. Level the unit carefully. Fully tighten the isolator
mounting bolts.
Figure 1 – Elastomeric Isolator
Isolator Pads Installation (Optional)
Isolators are ready to install. Mountings have to
be placed on a rigid and level foundation. External
equipment should not transmit additional vibration to
the chiller. The position of pads isolator is given in the
pad isolators installation or selection drawing which is
supplied with the chiller.
Figure 2 – Isolator pads