RLC-PRC020-EN

12

Selection
Procedure

Trane Series R chiller performance is
rated in accordance with the ARI
Standard 550/590-2003 Certification
Program. Chiller selection assistance and
performance information can be
obtained by using the Series R chiller
selection program, available through
local Trane sales offices.

Performance

The computerized Series R chiller
selection program provides performance
data for each possible chiller selection at
both full-load and part-load design points,
as required.

It should be noted that changing the
number of water passes or the water
flow rates will generally alter the
performance of a particular chiller. To
attain maximum benefit from the wide
range of chiller models and options
available, designers are encouraged to
first develop performance specifications
and then use the chiller selection program
to optimize all selections. This will help
ensure selection of the compressor-
evaporator-condenser combination that
most closely meets the job requirements.
To optimize system performance, all
selections should also be balanced with
other system components.

Fouling Factors

ARI Standard 550 includes a definition of
clean tube fouling. The recommended
standard fouling adjustments are 0.0001
hr-sq ft-deg F/Btu (0.0176 sq m-deg C/kW)
for the evaporator and 0.00025 hr-sq ft
deg F/Btu (0.044 sq m-deg C/kW) for the
condenser, from an increment of 0.0000
“clean.” Chiller specifications should be
developed using the most current
standard fouling factors.

Part Load Performance

Actual air-conditioning system loads are
frequently less than full-load design
conditions. Depending on the number of
chillers on the job and the load profile,
chillers may operate at full load a small
percentage of the time. With their
excellent part-load performance
characteristics and highly energy-efficient
operation, Series R chillers can provide
significant operating savings at these
part-load conditions.

System Considerations

Part-load chiller operation is frequently
associated with reduced condenser
water temperatures. However, rather
than focusing only on the chiller, it is
important to balance these temperatures
to achieve the most efficient system
operation possible. At part-load
operation, the heat rejected to the cooling
tower is less than at full-load operation.

Part-load chiller operation is also typically
associated with reduced outside wet bulb
temperatures, resulting in improved
cooling tower performance. The net result
of reduced heat rejection and lower wet
bulb temperatures can be cooler
condenser water entering the chiller,
ultimately improving unit performance.
However, this does not improve pump or
tower efficiency. To achieve the most
efficient system operation possible, it is
best to minimize the total power draw of
the chiller, tower, and pumps, which may
not mean limiting the condenser water
temperature to what the tower can
provide. To determine specific unit and
system part-load performance for chiller
selection purposes, use the Series R
chiller computer selection program or
contact the local Trane sales office.

Содержание RTHD

Страница 1: ...SeriesR HelicalRotary LiquidChillers Model RTHD 175 450T ons 60 Hz 125 450T ons 50 Hz Built for Industrial and Commercial Applications RLC PRC020 EN June 2006...

Страница 2: ...n via the LCD touch screen display freedom from interoperability concerns with LonMark communications job specific communication options that allow greater reporting flexibility Improved startup tempe...

Страница 3: ...ures and Benefits Options Controls Application Considerations Selection Procedure Model Nomenclature General Data Electrical Data and Connections Dimensions andWeights Mechanical Specifications Conver...

Страница 4: ...mal Storage Specifiers and operators benefit from dual setpoint control and industry leading temperature efficiency and control capabilities plus outstanding support through partnership with Calmac a...

Страница 5: ...rovides maximum efficiency high reliability and low maintenance requirements Electronic expansion valve with fewer moving parts than alternative valve designs offers highly reliable operation Suction...

Страница 6: ...2 4 and 203 2 mm sizes Nitrogen Charge Unit is shipped with a nitrogen holding charge in lieu of refrigerant Seal Kit for Reassembly Ideal for situations when the bolt together construction of the RTH...

Страница 7: ...ice making and daytime comfort cooling Options Programmable Relays Default set factory installed programmable relays allow the operator to select four relay outputs from a list of eight Available rel...

Страница 8: ...on including normal cooling and icemaking Water temperatures and setpoints Loading and limiting status and setpoints Average line current Outdoor air temperature Start stop differential timers Auto Ma...

Страница 9: ...ng In the event of a problem the operator receives an alarm notification and diagnostic message to aid in quick and accurate troubleshooting A snapshot report showing system status just prior to an em...

Страница 10: ...to obtain and maintain this differential at startup but for continuous operation a design should maintain a 25 F 13 9 C differential from evaporator leaving water temperature to condenser leaving wat...

Страница 11: ...s This ideal balance of design integrity with installation and operating cost considerations can also be obtained by consulting aTrane representative and applying theTrane System Analyzer program Wate...

Страница 12: ...developed using the most current standard fouling factors Part Load Performance Actual air conditioning system loads are frequently less than full load design conditions Depending on the number of ch...

Страница 13: ...Performance with Fluid Media OtherThanWater Series R chillers can be provided with a wide variety of fluid media other than water including ethylene glycol and propylene glycol in the evaporator conde...

Страница 14: ...C UL Digit 13 Pressure Vessel Code A ASME L Chinese Pressure Vessel Code Digit 14 Evaporator Frame B B Frame C C Frame D D Frame E E Frame F F Frame G G Frame Digit 15 Evaporator Capacity 1 Tube coun...

Страница 15: ...igit 43 Power Line Connection Type A Terminal Blocks B Mechanical Disconnect Switch D Circuit Breaker F High Interrupt Circuit Breaker H Ground Fault Circuit Breaker J Ground Fault High Interrupt Circ...

Страница 16: ...B2 B2 B2 45 170 29 110 HFC 134a 410 186 B2 C2 D2 58 220 34 129 HFC 134a 490 222 C1 D6 E5 45 170 29 110 HFC 134a 490 222 C1 D5 E4 52 197 32 121 HFC 134a 490 222 C1 E1 F1 82 310 60 226 HFC 134a 525 238...

Страница 17: ...114 200 17 76 200 D2 28 125 200 19 83 200 D3 31 134 200 20 89 200 D4 22 97 200 15 65 200 D5 22 97 200 15 65 200 D6 18 81 200 12 54 200 E1 28 125 200 19 83 200 F1 36 156 250 24 104 200 F2 38 168 250 2...

Страница 18: ...200 21 76 200 D2 34 125 200 23 83 200 D3 37 134 200 25 89 200 D4 27 97 200 18 65 200 D5 27 97 200 18 65 200 D6 22 81 200 15 54 200 E1 28 125 200 23 83 200 F1 43 156 250 29 104 200 F2 46 168 250 31 11...

Страница 19: ...ta 50 Hertz NominalVoltage 380 400 415 Compressor Voltage 342 360 374 Code Utilization Range 418 440 457 Max kW 139 145 148 B1 B2 RLA Max kW 233 233 233 LRA Y 391 412 428 LRAD 1229 1296 1348 Max kW 20...

Страница 20: ...RLC PRC020 EN 20 Electrical Data and Connections...

Страница 21: ...21 RLC PRC020 EN Electrical Data and Connections...

Страница 22: ...3 17 560 7 965 16 168 7 334 D1 D1 E1 15 385 6 978 14 443 6 551 D1 F1 F2 17 537 7 955 16 187 7 342 D1 G1 G1 20 500 9 299 18 600 8 437 D1 G2 G2 21 065 9 555 19 107 8 667 D2 D3 D2 E2 15 570 7 062 14 562...

Страница 23: ...erEnd 36 914 mm OtherEnd 108 2743 mm T op 36 914 mm Clearance for tube removal Note 1 Dimensions are based on 3 Pass Evap 2 Pass Cond and LH LH water connections Refer to submittals for exact configur...

Страница 24: ...erEnd 36 914 mm OtherEnd 126 3200 mm T op 36 914 mm Clearance for tube removal Note 1 Dimensions are based on 3 Pass Evap 2 Pass Cond and LH LH water connections Refer to submittals for exact configur...

Страница 25: ...EitherEnd 36 914 mm OtherEnd 108 2743 mm T op 36 914 mm Clearance for tube removal Note 1 Dimensions are based on 3 Pass Evap 2 Pass Cond and LH LH water connections Refer to submittals for exact conf...

Страница 26: ...erEnd 36 914 mm OtherEnd 126 3200 mm T op 36 914 mm Clearance for tube removal Note 1 Dimensions are based on 3 Pass Evap 2 Pass Cond and LH LH water connections Refer to submittals for exact configur...

Страница 27: ...EitherEnd 36 914 mm OtherEnd 126 3200 mm T op 36 914 mm Clearance for tube removal Note 1 Dimensions are based on 3 Pass Evap 2 Pass Cond and LH LH water connections Refer to submittals for exact conf...

Страница 28: ...therEnd 36 914 mm OtherEnd 126 3200 mm T op 36 914 mm Clearance for tube removal Note 1 Dimensions are based on 3 Pass Evap 2 Pass Cond and LH LH water connections Refer to submittals for exact config...

Страница 29: ...530 microprocessor automatically acts to prevent unit shutdown due to abnormal operating conditions associated with low evaporator refrigerant temperature high condensing temperature and or motor curr...

Страница 30: ...RLC PRC020 EN 30 ConversionTable...

Страница 31: ...31 RLC PRC020 EN...

Страница 32: ...specifications without notice Literature Order Number File Number Supersedes Stocking Location Trane A business ofAmerican Standard Companies www trane com For more information contact your local sal...

Отзывы: