Installation
20
RT-SVX39B-EN
•
Install and connect a condensate drain line to the
evaporator drain connection.
Note:
Condensate Overflow Switch will not work if unit is
not level, or slightly sloped toward switch.
Factory Installed Economizer
•
Ensure the economizer has been pulled out into the
operating position. Refer to the economizer installers
guide for proper position and setup.
•
Install all access panels.
Horizontal Discharge
Conversion WSC060E
•
Supplies Needed by Installer for Conversion: 3 oz. tube
of High Temperature RTV sealant. (500°F/260°C:
Similar to Dow Corning 736)
Note:
Failure to use recommended sealant could result in
unit performance loss.
If a unit is to be converted to a horizontal discharge, the
following conversion must be performed:
1.
Remove RETURN and SUPPLY duct covers.
2. Locate supply cover. Apply ¼ in. (6mm.) continuous
bead of 500°F RTV sealant to the flange as shown.
3. Position SUPPLY DUCT COVER as shown, rotate 90
degrees to allow entrance into supply opening.
4. Slide SUPPLY DUCT COVER into duct openings until
inward edge of duct cover engages with the 2 retaining
clips on the duct flanges. Secure the outward edge of
each duct cover with 2 screws.
5. Slide RETURN DUCT COVER (insulation side up) into
supply opening until inward edge of duct cover
engages with the 2 retaining clips on the duct flange.
Secure outward edge of the duct cover with two
screws.
Horizontal Discharge Conversion WSC072-
120E
•
Supplies Needed by Installer for Conversion: 3 oz. tube
of high Temperature RTV sealant. (500°F/260°C:
Similar to Dow Corning 736)
Note:
Failure to use recommended sealant could result in
unit performance loss.
If a unit is to be converted to a Horizontal discharge, the
following conversion must be performed:
1.
Remove RETURN and SUPPLY duct covers.
2. Place SUPPLY DUCT COVER over down-flow return
opening. (insulation side down)
3. Using self-drilling screws, (or screws removed from
duct cover), screw through dimples to attach DUCT
COVER to base.
4. On original RETURN DUCT COVER, apply ¼” (6mm.)
continuous bead of 500°F RTV sealant around flange
(opposite insulation side), as shown.
5. Slide RETURN DUCT COVER (insulation side up) into
supply opening until inward edge of duct cover
engages with the 2 retaining clips on the duct flange.
Secure outward edge of the duct cover with two
screws.
Figure 16.
Figure 17.
RTV Sealant
Supply duct cover with
RTV installed
Figure 18.
Figure 19.
Supply Duct Cover
Screw into 4
dimples on top
edge
RTV Sealant