12
ARTC-SVX001B-EN
Table 2. Initial startup readiness checklist (continued)
☐
☐
Startup Readiness Dimension
☐
Check the box if high voltage wiring is installed, tested, and functional.
☐
Check the box if all water, refrigeration, and electrical connections between chiller modules are completed.
☐
Check the box if all control wiring between modular chillers is installed, tested, and functional.
☐
Check the box if control wiring is complete, including any additional remote interface panel or special-purpose wiring.
☐
Check the box if all responsible installing contractors and sub-contractors have been notified to have representatives available on site to
provide technical support for the initial start-up procedure.
☐
Check the box if full load will be available for chiller on the initial start-up date.
☐
Touchscreen Interface Panel: Record version and date of the software loaded into the touchscreen interface panel:
Version: ____________________________________ Date: ________________
Note:
To view the software version, from the home screen, press the software button on the System Control screen.
Startup
As part of a continuous commitment to quality, initial
startup of this chiller must be done by Trane.