Repair to Intrinsically Safe Components
- Do not apply any permanent inductive or capacitance loads to the circuit without ensuring that this will not exceed
the permissible voltage and current permitted for the equipment in use.
- Intrinsically safe components are the only types that can be worked on while live in the presence of a flammable
atmosphere.
- Replace components only with parts specified by the manufacturer. Other parts may result in the ignition of
refrigerant in the atmosphere from a leak.
Cabling
- Check that cabling will not be subject to wear, corrosion, excessive pressure, vibration, sharp edges or any other
adverse environmental effects. The check shall also take into account the effects of aging or continual vibration
from sources such as compressors or fans.
Detection of Flammable Refrigerants Removal and Evacuation
- The refrigerant charge shall be recovered into the correct recovery cylinders and the system shall be “flushed”
with OFN to render the unit safe. This process may need to be repeated several times.
- Compressed air or oxygen shall not be used for purging refrigerant systems.
- Flushing shall be achieved by breaking the vacuum in the system with OFN and continuing to fill until the working
pressure is achieved, then venting to atmosphere, and finally pulling down to a vacuum. This process shall be
repeated until no refrigerant is within the system. When the final OFN charge is used, the system shall be vented
down to atmospheric pressure to enable work to take place.
- The vacuum pump is not close to any ignition sources and that ventilation is available.
Charging Procedures
- Ensure that contamination of different refrigerants does not occur when using charging equipment. Hoses or lines
shall be as short as possible to minimise the amount of refrigerant contained in them.
- Cylinders shall be kept upright.
- Ensure that the refrigeration system is earthed prior to charging the system with refrigerant.
- Label the system when charging is complete (if not already).
- Extreme care shall be taken not to overfill the refrigeration system.
- Prior to recharging the system, it shall be pressure-tested with the appropriate purging gas. The system shall be
leak- tested on completion of charging but prior to commissioning. A follow up leak test shall be carried out prior
to leaving the site.
Decommissioning
- Before carrying out this procedure, it is essential that the technician is completely familiar with the equipment and
all its detail.
- Prior to the task being carried out, an oil and refrigerant sample shall be taken in case analysis is required prior to
re-use of reclaimed refrigerant.
- Electrical power must be available before the task is commenced.
Содержание 4TXM2318BF300AA
Страница 102: ...100 PCB 0151800611 4MXE2309BF0W0AA 4MXE2312BF0W0AA...
Страница 116: ...114 PCB 0151800364D Power Module 0011800377C...
Страница 117: ...115 Power Module 0011800377AJ PCB 0151800364C...
Страница 153: ...151 Screw 0010600325 Terminal block 0010452210E Connection cable 0150400330 Install the connection cable like this way...