ordering them to satisfy the load of the machine and the maximum weight of the workpiece
(~10,000 lb.).
8.
When machine is correctly leveled, lock the adjusting screws in place with their hex nuts. See
figure 2.6.2a.
Figure 2.6.2a
Figure 2.6.2b
2.6.3 Adjusting Level for Tram
1.
Moun
t the .0001” test indicator to the spindle nose and sweep the table with a 12” span (6”
radius).
2.
If the tram measurement is not .0008 TIR on the VMC7 and VMC10, adjust the R3 and L3
leveling bolts to adjust the tram within specification. This will tend to help adjust any error you
have in the Y axis for the tram. By adjusting these bolts, you can in affect slightly affect the
column and bring in the tram.
3.
If the tram measurement is not .0008 TIR on the VMC5, adjust the R2 and L2 leveling bolts to
adjust the tram within specification. This will tend to help adjust any error you have in the Y axis
for the tram. By adjusting these bolts, you can in affect slightly affect the column and bring in
the tram.
4.
Once complete, lock all leveling screws in place with the lock nuts. See figure 2.6.2a
2.7 Shortages: Inventory Checklist
The following items will come standard with the VMC. Please note any optional items that have been
ordered are present.