29
TRIAD Boiler Systems, Inc.
West Chicago, IL
www.triadboiler.com
Safety relief valves (SRV) are selected and sized to the ASME boiler and pressure vessel code. Connections
for SRV(s) are provided along the top centerline of the boiler. Connection 1” and larger not slated for use
have an appropriate pipe nipple and cap installed.
Locations and sizes of many components are specified in the dimensional data and drawings.
An instrumentation cluster is provided in the outlet spool as detailed in section 2.2. These connections
are typically used for three aquastats, a temperature, and a pressure gauge. The low water cutoff will be
a probe connection in this spool. The temperature and pressure gauge may be replaced with a tridicator.
The High limit, Operating, and Firing rate controls are installed as individual components in the boiler
outlet spool instrumentation cluster. Stop valves are not to be installed between the boiler and any of
these controls. These controls occupy three of the connections of the instrumentation cluster with
aquastats. The Firing rate controller can be replaced with a temperature sensor that is incorporated into
the burners controls. The operator and firing rate controls can be incorporated into the same device.
The water supply nozzles are ANSI class 150# flange. TRIUMPH SS boilers come with a medium and a low
temperature water return nozzle along the centerline above the flue gas outlet. If only one nozzle is used
always use the low temperature return. Recirculation pump connections and re-circulating pumps may
be added to one or both sides of the boiler to isolate the boiler from the hot water system and reduce
temperature differential across the boiler. The boiler shall have a drain connection.
4.0 BOILER INSTALLATION
4.1 Receiving the boiler
During the construction of your new boiler, over one hundred separate inspections were made of the unit.
It is good practice prior to accepting delivery to examine your boiler in detail to be sure that the unit has
not been damaged in transit. If damage is evident, make a notation on the freight bill of the damage and
file a claim against the carrier for the cost of replacement or repair. In the event the boiler-burner unit
has and concealed damage (damage which is not outwardly evident), you have up to fifteen (15) days
after receipt of the unit to file a claim covering repair or replacement of the concealed damage. Most
units are shipped with certain fragile and easily damaged parts packaged in a separate box.
Boilers are typically shipped with the main boiler burner package assembled with fuel train(s), mounted
switches, and wiring that is practical before placement. Electrical components are wrapped in plastic, and
the boilers internals are closed off from the elements. The shipped condition is only intended to protect
the boiler from weather during transport, not additional long term storage. Some parts are shipped loose
with the boiler. Boil out chemicals, if purchased from TRIAD are shipped separately.
Содержание Triumph 1000
Страница 14: ...14 TRIAD Boiler Systems Inc West Chicago IL www triadboiler com Handling Options ...
Страница 16: ...16 TRIAD Boiler Systems Inc West Chicago IL www triadboiler com 2 0 Boiler Component Identification ...
Страница 20: ...20 TRIAD Boiler Systems Inc West Chicago IL www triadboiler com Model 300 500 Model 750 1000 ...
Страница 27: ...27 TRIAD Boiler Systems Inc West Chicago IL www triadboiler com 2 6 Example wiring diagrams ...