3.3.2 Check the project table after installation
No.
Inspection item
Yes
No
Remarks
1
Whether the power supply voltage is
consistent with the requirements of the
2
Whether the components are installed
correctly
3
Whether the bolts, screws, nuts are tightened
Note:
Please fill in the inspection item list after the installation is finished.
3.4 Commissioning and debugging
Commissioning
After the installation of the machine but before the connection with the power supply,
it is necessary to determine the user's power supply, the gas source and the
requirements of the machine is consistent.
The machine is connected to the circuit, the circuit must be fitted with a fuse that is in
line with the operating rules. The automatic circuit breaker of 25A is required to be
operated by professional personnel. The power plug of the tire changer is provided
with the customer.
As shown in Figure 7, the compressed air system is connected to the machine by a
pipe joint (Q) on the side of the tank.
Figure 7