Telecell Installation Manual
Commissioning
TL-006175-PR Issue 5 © Telensa Ltd 2018
Page 26
3.5.2
Telecell Control
To test if a Telecell can be controlled and return meaningful data, use the
Polling
and
Override
functions within the PLANet user interface. The sequence is as follows:
1)
Poll the
Asset
(for the power parameter) and record the reading, found within the
Readings page –
Readings
>
Lamp Electrical
>
Power
.
2)
Override the
Asset
to
Full On
.
3)
Poll the
Asset
(for the power parameter) and record the reading, found within the
Readings page.
4)
Include if the dimming unit is installed -
Override
the
Asset
to
DIM2
.
5)
Include if the dimming unit is installed - Poll the
Asset
(for the power parameter)
and record the reading, found within the Readings page.
6)
Override the Asset to
Return to Normal Operation
.
7)
Poll the Asset (for the power parameter) and record the reading, found within the
Readings page. Confirm that the readings obtained are as expected in
accordance with the associated Lamp Type.
Note:
The Properties section can also be used to carry out this task on single
Assets if the User is familiar with this process.
3.5.2.1
Polling
1)
To Poll an Asset, navigate to the
Polling
page, select the
Asset
and
Parameter
to be polled and click the
Poll Asset
tab.
The progress of this task can be viewed within the
Tasks
>
Polling
page.