Telecell Installation Manual
Commissioning
TL-006175-PR Issue 5 © Telensa Ltd 2018
Page 25
3.4
Operational Checks
For a Telecell to be controlled and return meaningful data it must be set up correctly.
Ensure each Telecell is:
Connected
Assigned to an
Asset
Has a
Control Program
with appropriate dimming levels set within the
Power
tab
Has the correct
Lamp Type
and
Charge Code Assigned
(make a note of the
Circuit Watts within the Charge Code)
3.5
Bring the Telecell into Service
3.5.1
Connection Status
Once installed and powered, the Telecell should connect to the Central System within a
few hours. This can be confirmed by observing the Telecells Page within the User
Interface.
Filter the Telecell ID column for the OSID.
Note:
When a Telecell connects,
the Last Known Status
column symbol turns
green
and data
becomes present in the
Last Connection Confirmation
[data received] column. If the
Telecell is not connected, the Test and Commissioning phase cannot be completed.
Note:
The
Last Known Status
column is the result of either the success or failure of any last
communication with the Telecell.