TP350 User’s Manual
2. Installation
Use the following procedures when installing system.
1. Confirm that the system power switch is set to off.
2. Connect the system side of the power cable to the power connector on the rear
of the system.
3. Plug the AC power plug of the cable into power outlet.
The system is designed to operate normally with a 100 to 240V AC,50/60Hz
power line.
Make sure that the power outlet is designed for a 3-pronged plug
with ground line.
4. Turn on the system power.
5. The software starts as soon as power is applied.
Follow the installation procedures outlined in Chapter 4.System Operation.
3. Moving the System
Follow the procedures described below when moving the system to a new location
after it has been installed.
●
New Location Within the Same Site
Follow the precautions listed below when moving the system to a new location
within the same site.
1. Thoroughly clean the system and make sure that there are no tubes or plates
remaining in the sample block.
2. Avoid any shock during movement that can affect the operation of this highly
sophisticated system.
3. When lifting and carrying the system, be sure to place one hand on either side
of the system and lift and carry in a balanced way.
4. Make sure that the new location conforms to the installation requirements
described in section “1
.
Installation Conditions” in Chapter 2.
5. Follow the installation procedures outlined in section “Installation” in Chapter
2.
●
Moving to a New Site
When moving the system to a new site, clean it carefully and repack it in the
packaging in which it was delivered. Note that damage sustained by the system
during transport due to improper packaging will not be covered by Warranty period
is still valid. Follow the instructions provided in this chapter when reinstalling the
system at the new location.
In the interests of safety, and avoiding electric
shocks, be sure to connect the system to a
properly grounded power outlet.
CAUTION
!
v
2.01
10