4. Transport and Access
4.1 Heat Pump
4.2 HydroBox
A pallet should be used to transport the heat pump to its final installation
location. The basic device can be transported with a lift truck, hand truck
or by means of 3/4" pipes fed through the holes in the baseplate or frame.
Before using the transport holes in the frame, it is necessary to remove the
side sections. To do this, loosen the two screws at the top, tilt the metal
plate to the side and remove at the top (see Fig 3 steps 1-3)
Once the side sections have been removed, the outdoor unit can be lifted
by the cover. To do this, loosen the two screws at the top, tilt the metal plate
to the side and remove at the top (see Fig 3 steps 1-3)
Be careful not to damage any components or cables when inserting the
pipes through the frame.
See Section 5.1 for recommended clearances for installation and
maintenance.
Important:
After the final positioning at the installation location, remove the
transport fastening on the sprung floor of the compressor on both sides.
Remove the two screws in the middle location on both sides. Do not
remove or alter the location of the nuts or screws at the four corners of the
sprung floor. (See Fig. 4)
A pallet is supplied to ease transport of the HydroBox to its final installation
location. The basic device can be transported with a lift truck or hand truck.
Access to the line and low voltage wiring hub is achieved by removing just
the left side panel. To do this, loosen the six screws, pull the panel out about
1" and then lift straight up to disengage the L brackets from the frame with
the help of the hand grips. (See fig. 5, steps 1-3)
The condensate drain line is installed through the hole in the bottom of the
right panel. The connection is 1/2" NPT. The right panel does not need to be
remove for initial installation but if access to the right side is needed to ease
access during service, the condensate drain line needs to be disconnected
before removing the panel. The front and rear panels do not need to be
removed for installation. See Section 5.3 for recommended clearances for
installation and maintanence.
Caution:
The outdoor unit with refrigeration circuit must not be
tilted more than 45° (in any direction).
Caution:
Before commissioning, the transport fastening must be
removed.
www.glendimplex.de
452169.66.04 · FD 0007
5
Air-/Water-Chiller-Heatpump
English
4 Transport
4.1 Monoblock
A pallet should be used to transport the chiller-heat pump to its
final installation location. The basic device can be transported
with a lift truck, hand truck or by means of 3/4" pipes fed
through the holes in the baseplate or frame.
!!
CAUTION!
The outdoor unit with refrigeration circuit must not be tilted
more than 45° (in any direction).
Once the side sections have been removed, the outdoor unit
can be lifted by the cover. To do this, loosen the two screws at
the top, tilt the metal plate to the side and remove at the top
(see steps 1-3)
Before using the transport holes in the frame, it is necessary to
remove the side sections. To do this, loosen the two screws at
the top, tilt the metal plate to the side and remove at the top
(see steps 1-3)
Be careful not to damage any components or cables when in-
serting the pipes through the frame.
After the final positioning at the installation location, remove
the transport fastening on the sprung floor of the compressor
on both sides.
!!
CAUTION!
Before commissioning, the transport fastening must be re-
moved.
1.
2.
3.
1.
www.glendimplex.de
452169.66.04 · FD 0007
5
Air-/Water-Chiller-Heatpump
English
4 Transport
4.1 Monoblock
A pallet should be used to transport the chiller-heat pump to its
final installation location. The basic device can be transported
with a lift truck, hand truck or by means of 3/4" pipes fed
through the holes in the baseplate or frame.
!!
CAUTION!
The outdoor unit with refrigeration circuit must not be tilted
more than 45° (in any direction).
Once the side sections have been removed, the outdoor unit
can be lifted by the cover. To do this, loosen the two screws at
the top, tilt the metal plate to the side and remove at the top
(see steps 1-3)
Before using the transport holes in the frame, it is necessary to
remove the side sections. To do this, loosen the two screws at
the top, tilt the metal plate to the side and remove at the top
(see steps 1-3)
Be careful not to damage any components or cables when in-
serting the pipes through the frame.
After the final positioning at the installation location, remove
the transport fastening on the sprung floor of the compressor
on both sides.
!!
CAUTION!
Before commissioning, the transport fastening must be re-
moved.
1.
2.
3.
1.
Fig. 3
Fig. 4