62
step 4 Follow the foregoing steps to connect PV connectors of other PV strings.
step 5 Seal any unused PV terminal with a terminal cap.
- - End
5.8
Wiring of Tracking System Power Cable (Optional)
step 1 Refer to step 1 to step 2 described in
5.6.3 Connection Procedure of One Wire per Phase
.
step 2 Cut off excess sealing ring according to the outer diameter of the cable.
step 3 Lead the cable with the protective layer removed through the sealing ring. Retain 50mm of
cable with the protective layer in the AC junction box.
User Manual