These instructions are intended for correct installation of power beyond on a Salami VDM8
valve bank. If any hydraulic component is integrated after this valve the power beyond
must be installed correctly, or serious damage may incur to the hydraulic system.
1. Remove cover/access plug to reveal the power
beyond access point. Can also be used as the
Return/Tank port.
2. Install a 3/8” straight thread pipe plug into lower por-
tion of cavity to activate the power beyond feature.
Use thread sealer (tape sealers not recommended.
3. The Power Beyond feature is now activated and will
divert oil to alternate system via the port shown.
Power Beyond VDM8 Valve
Note:
1. The return/tank line must be connected to the
top or the side port, labeled “T”.
2. Using the return line to run auxillary equipment will
directly result in a failure and will not in any cir-
cumstance be covered under warranty.
3. A standard Stellar hooklift will have 6 hydraulic
lines attached to the valve. A Stellar hooklift with
Power Beyond will have 7 hydraulic lines
attached to the valve.
Port Relief Location for Hoists with Inside Latches
NOTE: Install port relief PN26182 here
when using inside latches or latches
with stops.
Содержание Slider50
Страница 2: ...Slider50 Hooklift Manual Revisions Date of Revision Description of Revision Section Revised...
Страница 10: ...4 Slider50 Owner s Manual...
Страница 22: ...16 Slider50 Owner s Manual...
Страница 25: ...19 Acceptable Subframe Dimensions for Bodies...
Страница 26: ...20 Slider50 Owner s Manual Acceptable Subframe Dimensions for Bodies...
Страница 27: ...21 Acceptable Subframe Dimensions for Bodies...
Страница 28: ...22 Slider50 Owner s Manual Acceptable Subframe Dimensions for Bodies...
Страница 60: ...54 Slider50 Owner s Manual...