Maintenance
08|2018 EN
25
8 Maintenance
NOTICE
Before
maintenance
work, close all shut-off valves and drain
all pipes.
All pumps
When?
What?
Regularly
Clean
strainer
basket.
If there is a chance of
frost
Drain pump and pipes sensitive
to frost in good time.
Additionally for pumps with plastic lanterns (AK version)
When?
What?
Regularly
Remove salt crystals caused by
the salt water. See point 8.3 on
page 27
Prior to longer idle
periods
Rinse the pump with tap water
to prevent crystals from forming
on the mechanical seal.
After completing all maintenance work, perform all necessary
measures for start-up. See point 6.1 on page 21
Service addresses can be found on our website
www.speck-pumps.com
.
8.1 Installing
or
removing the lid/strainer basket
Any lids and strainer baskets must be removed for work to be
performed. See 8.1 in the associated pump data sheet.