Adding the Process Fluid
At this point the Ultra-Cool should be hooked up to the proper electrical service and all
plumbing necessary for operation should be in place and sealed.
Make sure the drains are closed. These are two black hoses at the rear of the
1.
unit. Both drain lines should be plugged and have hose clamps to ensure the
plugs stay in place.
Plug in the provided 9-pin jumper (jumps pins 5 & 6) into the Remote EMO.
2.
Switch ON the breaker on the back of the machine.
3.
The white MAINS light should illuminate.
4.
Pull out the red PUSH TO STOP button.
5.
One bar will be displayed on the LED (indicating the reservoir is empty).
6.
LED
Fluid Level
Alarm
_ _ _ _
Reservoir Full
Reservoir full
_ _ _
Normal
Normal operation level
_ _
Fluid Low
Flashes “rEFL” (Refill)
_
Critical Level
Alarms sound, unit shuts down.
ALWAYS USE CAUTION WHEN HANDLING FLUIDS, FILLING OR DRAINING THE SYSTEM
RESERVOIR, OR WORKING IN OR AROUND THE CHILLER.
ALWAYS WEAR PROTECTIVE EYEWEAR WHEN OPERATING THE CHILLER.
To add fluid:
Remove the reservoir cap on the top of the unit.
7.
Add process fluid to reservoir.
8.
The LED will display _ _ _ _ (indicating the reservoir is full).
9.
Press the green START button.
10.
Содержание ULTRA-COOL
Страница 1: ...RECIRCULATING CHILLER OPERATOR S MANUAL ULTRA COOL WITH MPC CONTROL...
Страница 2: ......
Страница 6: ...iv Rev 008 01 12 SP Scientific 2012...
Страница 10: ...Introduction Ultra Cool 2 Rev 008 01 12 SP Scientific 2012...
Страница 26: ...System Control Ultra Cool 18 Rev 008 01 12 SP Scientific 2012...
Страница 34: ...System Control Ultra Cool 26 Rev 008 01 12 SP Scientific 2012...
Страница 38: ...Maintenance Ultra Cool 30 Rev 008 01 12 SP Scientific 2012...
Страница 58: ...RS 232 Programmer s Reference Ultra Cool 50 Rev 008 01 12 SP Scientific 2012...
Страница 63: ......