9 Initial start-up
Connect the motor of the container auger
►
Connect the pre-routed cable as shown in the ter-
minal area of the motor.
Abb. 2-71: Connect the cable in the motor terminal area
9 Initial start-up
i
Initial commissioning of the boiler may only be
performed by qualified personnel
(SOLARFOCUS service technician or
SOLARFOCUS specialist service partner) (=
condition for guarantee, warranty).
Requirements
þ
The boiler is hydraulically connected.
þ
The heating system is filled with water and
has been vented.
þ
The boiler is electrically connected.
Commissioning
►
Connect the boiler to the mains power supply.
►
Carry out the
commissioning routine
in the boiler
control.
Complete the commissioning log, send it
i
Once commissioning is complete, the
completed commissioning log should be sent
to SOLARFOCUS. If this does not happen,
then for guarantee and warranty claims of any
kind the date of shipment from the
manufacturer to the dealer (according to the
delivery note and invoice) will be used.
10 Shut-down
Disassembly
–
Switch off the boiler and secure it against being
switched back on again.
–
Disconnect the boiler from the power supply.
–
Carry out disassembly in the reverse order to the
installation.
Disposal
–
Observe regional regulations in regard to pro-
per/environmentally-friendly disposal.
–
Recycle the recyclable materials.
Installation manual
maximus L
43
Содержание maximus L 150
Страница 16: ...Front Abb 2 10 Side view Abb 2 11 3 Technical requirements 16 Installation manual maximus L ...
Страница 44: ...11 Annex 11 1 Mounting boiler covers overview Abb 2 72 Abb 2 73 11 Annex 44 Installation manual maximus L ...
Страница 50: ...11 Annex 50 Installation manual maximus L ...
Страница 51: ...11 Annex Installation manual maximus L 51 ...