48
UPS for 400 Vac Grid, Installation Guide, doc. rel. 3.0
34.
You can now connect a load device to the ac output circuit breaker and then turn ON
the ac output circuit breakers on the electrical panel.
35.
If working with operating loads turn off the maintenance bypass circuit breaker to move
the load to the UPS.
36.
Transfer the load to inverter.
Do not transfer the load to the inverter if the maintenance bypass circuit breaker is
still in the ON position
(
Operation > Transfer load > Transfer to inverter
)
The Transfer load to inverter dialog appears:
Figure 30: Confirm Transfer Load to Inverter dialog
37.
Press
OK
.
38.
Update the last maintenance date. (
Main > Setup > System > Maintenance >
Maintenance Alarms List >Set last maintenance date)
.
The
Set Last Maintenance Date
screen appears:
Figure 31: Set Last Maintenance Date screen
Содержание Gamatronic B300
Страница 91: ...UPS for 400 Vac Grid Installation Guide doc rel 3 0 83 Figure 60 Connection diagram for 2 parallel units ...
Страница 92: ...84 UPS for 400 Vac Grid Installation Guide doc rel 3 0 Figure 61 Connection diagram for 4 Units in Parallel ...
Страница 95: ...UPS for 400 Vac Grid Installation Guide doc rel 3 0 87 7 1 Circuit Breaker Layout Figure 62 Electrical setup ...