2.1
ESTABISH ORIENTATION
i)
See Specifications for equipments ‘Minimum space’.
ii)
Measure out the site to ensure the space required fits into the allotted area, it is horizontal and free from
trip points or other obstructions.
iii)
Ensure the equipment is to be provided with an effective Impact Absorbing Surface which has a tested
critical fall height rating greater than the maximum freefall height of the equipment.
2.2
MARK OUT HOLES
Consult SMP layout drawing for structure position on site.
See FIG.3, 4 & 5 for concrete foundation spacings.
NOTE:
This is a minimum guide only. Hole excavation should be done progressively as the steelwork is erected.
2.3
ESTABLISH DATUM LEVEL
i)
If a rubber tiled Impact Absorbing surface is to be laid, see separate instructions (base may incorporate
up to 2% falls etc.).
ii)
If equipment is to sit in loose fill or wet pour rubber surfaces allowances will need to be made for its
recommended thickness. With certain loose fill materials, a greater thickness than 300mm may be
required. This will need to be determined by allowing 100mm for dispersal in addition to the thickness
required for the freefall height of the unit. For installation with a loose-fill type surface all legs on the
structure have be marked with a 'Basic Level Mark' to indicate the recommended 'Finished Surface Level'
of the surface.