Normal debugging work can’t be performed unless all installation items are qualified. If there is any problem, it
must be solved firstly. The installer will be responsible for all costs for delay of debugging and re-debugging
incurred by any problem which is not solved immediately.
Submit schedule of amending reports to installer.
Is the written amending report which should be signed after communication provided to installer?
Yes ( ) No ( )
5.2 Test run
Test run is testing whether the unit can run normally via preoperation. If the unit cannot run normally,
find and solve problems until the test run is satisfactory. All inspections must meet the requirements
before performing the test run. Test run should follow the content and steps of the table below:
The following procedure should be executed by experience and qualified maintenance men.
No.
Start up the pretest procedure
Notice: before test, ensure that all power must be cut off, including the far- end power switch, otherwise, it may cause
casualty.
1
Ensure that the compressor of the unit is preheated for 8h.
Caution: heat the lubricating oil at least 8h in advance to prevent refrigerant from mixing with the lubricating oil,
which may cause damage to the compressor when starting up the unit.
2
Check whether the oil temperature of the compressor is obviously higher than the outdoor ambient
temperature.
Caution: if the oil temperature of the compressor is obviously higher than the outdoor ambient temperature, it
means that the heating tape of compressor is damaged. In that case, the compressor will be damaged easily. Therefore,
repair the heating tape before using the unit.
3
Check whether the phase sequence of the main power supply is correct. If not, correct the phase sequence
firstly.
Recheck the phase sequence before start-up to avoid reverse rotation of the compressor which may damage the
unit.
4
Apply the universal electric meter to measure the insulation resistance between each outdoor phase and earth
as well as between phases.
Caution: defective earthing may cause electric shock.
No.
Ready to start
1
Cut off all temporary power supply, resume all the insurance and check the electricity for the last time.
Check the power supply and voltage of the control circuit; _____V must be ±10% within the range of rated
operating power.
No.
Start up the unit
1
Check all the conditions needed to start up the unit: oil temperature, mode, required load etc.
2
Start up the unit, and observe the operation of compressor, electric expanding valve, fan motor and water
pump etc.
Note: the unit will be damaged under abnormal running state. Do not operate the unit in states of high pressure
and high current.
Содержание S-THERM GSH-100ERB
Страница 5: ...Engineering Data Page 1 Total 145 ENGINEERING DATA...
Страница 15: ...Engineering Data Page 12 Total 145 2 Outline Dimensions GSH 60IRB GSH 80IRB GSH 100IRB...
Страница 16: ...Engineering Data Page 13 Total 145 GSH 80ERB GSH 100ERB GSH 60ERB...
Страница 18: ...Engineering Data Page 15 Total 145 SMH 80ERB...
Страница 21: ...SMH 100ERB Engineering Data...
Страница 23: ...SMH 60IRB...
Страница 24: ...SMH 60ERB...
Страница 26: ...Design and Selection Page 19 Total 145 DESIGN SELECTION...
Страница 40: ...Control Page 33 Total 145 UNIT CONTROL...
Страница 41: ...Control Page 34 Total 145 1 Integral Control Concept 1 1 Control Principle Diagram Control Diagram...
Страница 83: ...Control Page 76 Total 145 2 Open Ewpe Smart APP and click Sign up for registration...
Страница 85: ...Control Page 78 Total 145 4 Click at the right upper corner of homepage to add device...
Страница 88: ...Control Page 81 Total 145 3 3 2 Setting of Main Functions 1 Set mode and temperature...
Страница 91: ...Control Page 84 Total 145...
Страница 92: ...Control Page 85 Total 145 3 3 3 2 Help Click Help and view the operation instructions of the APP...
Страница 93: ...Control Page 86 Total 145 3 3 3 3 Feedback Click Feedback to submit feedback...
Страница 94: ...Unit Installation Page 87 Total 145 UNIT INSTALLATION...
Страница 98: ...Unit Installation Page 91 Total 145 3 Service Tools Name Picture Spanner Screw Driver Pliers Tube Tongs...
Страница 103: ...Unit Installation Page 96 Total 145 4 4 Outline Dimension of Outdoor Unit GSH 80ERB GSH 100ERB GSH 60ERB...
Страница 104: ...Unit Installation Page 97 Total 145 GSH 60ERB GSH 80IRB GSH 100IRB...
Страница 112: ...Unit Installation Page 105 Total 145 4 6 4 Outline dimension of indoor unit...
Страница 118: ...Unit Installation Page 111 Total 145...
Страница 125: ...Unit Installation Page 118 Total 145 GSH 80ERB GSH 100ERB GSH 60ERB...
Страница 126: ...Unit Installation Page 119 Total 145 4 11 Wiring of the Terminal Board GSH 60IRB GSH 80IRB GSH 100IRB...
Страница 135: ...Test Operation Troubleshooting Maintenance Page 128 Total 145 TEST OPERATION TROUBLESHOOTING MAINTENANCE...