5.
At the controller, in the Fault Table, the User is expected to ‘Acknowledge’ the change in
Node and then pre
ss the L3 button to confirm. Note: The use of the ‘Release’ Button is not
required.
9.5.4
Replacement of a Smartloop.
To replace a Smartloop, disconnect the unit from the RAG Node from which it is spurred by
disconnection at the PTB (see section 4.1).
Disconnecting a Smartloop affects all Smarloop nodes connected
downstream
Smartloops are not connected to the Plus+ network via a Bypass module. During replacement of a
Smartloop, communications to any Smartloops connected via the replaced Smartloop will be disrupted.
Once disconnected at the PTB, the Smartloop connections to the Plus+ network cable and the loop
feeder/tails cable can be cut as near to the respective torpedo resin joints as is practicable.
Take note of the New Serial Number
For a single Node, the process to acknowledge an update does not require prior knowledge of the Serial
Number. However, it is good practice to note the New Serial Number and update any backups of the
Design Layout (paper or Electronic). i.e. tack a photo of the QR code serial number
If multiple nodes are being replaced, then the Serial Number will need to be noted for configuration
update. i.e. tack a photo of the QR code serial numbers and note their respective locations
Connect the replacement Smartloop to the loop feeder/tails cable. See section 4.9.1 and 4.9.2 for
details.
See section 4.9.3 for instructions on confirming the correct installation and configuration of the
replacement Smartloop device in combination with the loop.
Connect the replacement Smartloop to the Plus+ network cable. See section 4.9.1 and 4.9.2 for
details.
Reconnect the Smartloop connection to the RAG Node from which it is to be spurred at the PTB.
At the controller, in the Fault Table, the User is expected to ‘Acknowledge’ the change in Node
and then press th
e L3 button to confirm. Note: The use of the ‘Release’ Button is not required.