7.2
Checks to be carried out prior to commissioning
Once the system has been correctly installed, you should check the following prior to
commissioning:
Note
Checks to be carried out prior to commissioning
The following list of checks to be performed prior to commissioning does not claim to be
complete. It may be necessary to perform further checks and tests in accordance with the
specific situation on-site.
● The machine is undamaged.
● The machine has been correctly installed and aligned, the transmission elements are
correctly balanced and adjusted.
● All fixing screws, connection elements, and electrical connections have been tightened to
the specified tightening torques.
● The operating conditions match the data provided in accordance with the technical
documentation, such as degree of protection, ambient temperature, etc..
● Moving parts such as the coupling move freely.
● All touch protection measures for moving and live parts have been taken.
● If the second shaft extension is not in use, its feather key is secured to prevent it from being
thrown out, and cut back to roughly half its length if the rotor has balancing type "H"
(standard type). The unused shaft extension is covered and protected against accidental
contact.
● The rotor can spin without coming into contact with the stator.
● The bearing insulation is not bridged.
Electrical connection
● The grounding and equipotential bonding connections have been made correctly.
● The machine is connected so that it rotates in the direction specified.
● Appropriately configured control and speed monitoring functions ensure that the motor
cannot exceed the permissible speeds specified in the technical data. For this purpose,
compare the data on the rating plate or, if necessary, the system-specific documentation.
● The minimum insulation resistance values are within tolerance.
● Minimum air clearances have been maintained.
● Any supplementary motor monitoring devices and equipment have been correctly
connected and are functioning correctly.
● All brakes and backstops are operating correctly.
● At the monitoring devices, the values for "Warning" and "Shutdown" are set.
Commissioning
7.2 Checks to be carried out prior to commissioning
SIMOTICS M-1PH8 1PH818., 1PH822., 1PH828.
Operating Instructions 10/2017
89
Содержание SIMOTICS M-1PH818
Страница 2: ...20 10 2017 15 09 V20 00 ...
Страница 14: ...Introduction SIMOTICS M 1PH8 1PH818 1PH822 1PH828 14 Operating Instructions 10 2017 ...
Страница 28: ...Description SIMOTICS M 1PH8 1PH818 1PH822 1PH828 28 Operating Instructions 10 2017 ...
Страница 66: ...Mounting 5 5 Refitting the external fan SIMOTICS M 1PH8 1PH818 1PH822 1PH828 66 Operating Instructions 10 2017 ...
Страница 104: ...Operation 8 10 Faults SIMOTICS M 1PH8 1PH818 1PH822 1PH828 104 Operating Instructions 10 2017 ...
Страница 132: ...Maintenance 9 3 Repair SIMOTICS M 1PH8 1PH818 1PH822 1PH828 132 Operating Instructions 10 2017 ...
Страница 160: ...Disposal 11 4 Disposal of components SIMOTICS M 1PH8 1PH818 1PH822 1PH828 160 Operating Instructions 10 2017 ...
Страница 166: ...Quality documents SIMOTICS M 1PH8 1PH818 1PH822 1PH828 166 Operating Instructions 10 2017 ...
Страница 171: ...171 ...
Страница 172: ...172 ...
Страница 173: ...173 ...
Страница 174: ...174 ...
Страница 175: ...175 ...
Страница 176: ...176 ...
Страница 177: ...177 ...
Страница 178: ...178 ...
Страница 179: ...179 ...
Страница 180: ...180 ...
Страница 181: ...181 ...
Страница 182: ...182 ...
Страница 183: ...183 ...
Страница 184: ...184 ...
Страница 185: ...185 ...
Страница 186: ...186 ...
Страница 187: ...187 ...
Страница 188: ...188 ...
Страница 189: ...189 ...
Страница 190: ...190 ...
Страница 191: ...191 ...
Страница 192: ...192 ...
Страница 278: ...278 ...
Страница 308: ...308 ...