Using the MJ-XL Operator Panel and Controls
Siemens Power Transmission & Distribution, Inc.
9
Tap Control Switches
Remote/Auto/Manual Switch (Mode Select
Switch)
This three-position switch determines whether the MJ-X
L
Control Panel is under manual control, microprocessor
control, or remote control. Note that the ultimate determi-
nation of the point of control is established manually; this
switch setting cannot be overridden from a remote loca-
tion.
•
Manual (By-Pass Position), The operator has control
of the regulator’s tap changer motor; automatic tap
changes are disabled. In this mode, a local operator
can use the Tap Raise/Lower switch to adjust the tap
position. A remote operator cannot exercise control
of the tap changer motor or the microprocessor, but
MJ-X
L
Control Panel data can be obtained.
•
Local-Auto. The microprocessor has control of the tap
changer motor and manual tap changes are disabled.
In this mode, a remote operator can obtain MJ-X
L
Control Panel data. However, the remote operator
cannot make configuration changes or exercise con-
trol of the tap changer motor.
•
Remote (Enable). The microprocessor has control of
the tap changer motor and manual tap switch
changes are disabled. In this mode, a remote opera-
tor has access to all functions available to the local
operator, including the ability to override automatic
control of the tap changer motor.
Tap Raise/Lower Switch
When the Remote/Manual/Auto switch is in Manual posi-
tion, this three-position switch activates the tap changer
motor to raise or lower the tap position.
Switch Positions for Bypassing
The front panel switches must be in the following posi-
tions before bypassing the regulator.
•
Power Switch - OFF
•
R/A/M Switch - Manual
•
Raise/Lower Switch - Off
2.6
Binding Posts
Front panel binding posts are dual banana-style
receptacles on standard 0.74 inch centers.
External Source Binding Posts
These binding posts can be used to apply 120 V external
power to the MJ-X
L
Control Panel when the power source
switch is in the External Source position. The binding
posts are dual banana-style receptacles.
Note: Ensure that any voltage source attached to
these binding posts is properly polarized.
Voltage Calibration (Test) Binding Posts
These binding posts can be used with an external voltme-
ter to monitor regulator P2 or U2 voltage. The Voltage Cal-
ibration Key (U2/P2) defines which voltage (U2 or P2) you
can read at these binding posts. The binding posts are
dual banana-style receptacles.
Note that the voltage measured at these binding posts is
not turns-ratio corrected. By contrast, the metered voltage
presented on the display screen (under <
METER
>) is cor-
rected by control-program software. (See Section 4.3.6
and Section 4.3.7 for configuring the voltage transformer
U2/P2 turns ratio).
DANGER
Possible explosion can cause death,
serious injury or property damage.
To prevent:
The regulator must be placed in neutral
before by-passing. See Appendix E for
details.
CAUTION
Improper external source connection will
place 120V on the ground circuit.
May result in minor or moderate injury
including equipment damage.
To prevent:
Observe proper polarity of external power
supply.
WARNING
Voltage applied at calibration terminals may
energize regulator to high voltage through
voltage transformer.
Could result in death or serious injury.
To prevent:
Do not connect any voltage source at the
voltage calibration terminals.