Medical Solutions
Leakage current measurement
0
Transferring the values from the test protocol to the "device leakage current" proto-
col
NOTE
If the programmed line voltage has not been changed from its sta-
tus at delivery, and there have been no changes of parts in the
system's primary circuit, the device leakage current value speci-
fied in the test protocol delivered with the system is valid.
The device leakage current test need not be performed.
The value recorded in the test protocol must be used as the "first
measured value" in the "Device Leakage Current" protocol.
Perform the device leakage current measurement if the conditions
specified above do not apply.
Refer to the section "Device leakage current measurement during
start-up (if necessary)".
•
Complete the "Device leakage current" protocol found in the "Protocol" section of this
manual.
•
Enter the system serial number on the "Serial Number" row of the "Device leakage cur-
rent" protocol.
•
If applicable, enter the customer-specific system ID number in the "Customer-specific
ID Number" row of the "Device leakage current" protocol.
•
In test protocol 1, table "Alternative leakage current measurement (DIN VDE 0751)" or
"Device leakage current measurement (DIN VDE 0751-1), read off the higher recorded
value between rows "Leakage current under normal operation and with nominal volt-
age" and "Leakage current with power reversion of polarity and nominal voltage."
¹
Enter the higher value from test protocol 1 in the "Device leakage current" proto-
col, row "Device leakage current (highest measured value) [mA]" and in row
"Device leakage current corrected value [mA]", column "First measured value".
•
Read off the line voltage in test protocol 1 under "Revision Level".
¹
Enter the value from test protocol 1 in the "Device leakage current" protocol, row
"Line voltage during measurement [V~]", column "First measured value".
•
Read off the production resources entered in test protocol 1, table "Production
resources used".
¹
Enter the production resources from test protocol 1 in the "Device leakage cur-
rent" protocol, row "Measuring device: type", column "First measured value".
•
Read off the measuring device ID entered in test protocol 1, table "Production
resources used".
¹
Enter the measuring device ID from test protocol 1 in the "Device leakage cur-
rent" protocol, row "Measuring device, ser. no.", column "First measured value".
•
In "Device leakage current" protocol, row "(1) Meas. circuit", column "First measured
value", enter the text "VDE0751-1 Image C5".