23.5
FINAL ASSEMBLY TESTING PROCEDURES
In addition to the checks, tests, adjustments, measurements and calibrations the
individual PCBs go through, each fully assembled radio is also thoroughly tested before
being sent out to the customer. Though the actual tests are long and detailed, a listing of
the tests performed before any SG-2000 is shipped to a customer will indicate our
commitment to providing the best radio possible.
23.5.1
Pre Rack #1 Tests
The following are the tests performed on each SG-2000 before going on Rack #1
for 12 hours of continuous 100 W CW transmitting on 1.9 MHz into our light
bulb antenna load:
Serial number assignment
Bench inspection (visual, ohms, volts, etc.)
PLLs voltage check and adjustment
Receive SSB sensitivity check
Receive AM sensitivity check
AGC check
ALC 150/50 W transmit adjustment
Carrier insertion check and adjustment
150/50 W power check for for 1.6 to 30 MHz
Head functions check
Communication with SGC Base Station
Antenna mismatch protection in transmit
Recovery at power supply failure
135 W RF Out spectrum quality adjustment
RS-232 port check
11.94 oscillator check
Installation on Rack #1 for 12 hour transmit test and Test Log entry