Installation
AC output cable connection
PE cable should be connected properly and
reliably
Don’t reversely connect PV input cable and
battery input cable to interfaces!
Don’t reversely connect AC Backup load
connector and AC Grid connector.
STEP 1:
Cable OD 16-20mm, pry inner ring out of connector.
STEP 2:
The connector and cable are required to be reliably
connected as shown below.
Order of connection is 1-A
(
Yellow
)
, 2-B
(
Green
)
, 3-
C
(
Red
)
, 4-N
(
Blue
)
,-PE
Cable sectional area 6 mm², stripping length 10
±
0.5mm
Содержание SMT-10K-TL-TH
Страница 1: ...Basic Introduction to Hybrid Inverter SMT 10K TL TH...
Страница 5: ...2021 8 19 www sermatec ess com 5 Technical Parameters...
Страница 6: ...2021 8 19 www sermatec ess com 6 Technical Parameters...
Страница 14: ...2021 8 19 www sermatec ess com 14 Installation...
Страница 19: ...2021 8 19 www sermatec ess com 19 Installation...
Страница 20: ...2021 8 19 www sermatec ess com 20 Installation...
Страница 25: ...2021 8 19 www sermatec ess com 25 Installation Notes 4 Wiring diagram of 10K...
Страница 37: ...2021 8 19 www sermatec ess com 37 Maintenance Routine Maintenance...
Страница 38: ...2021 8 19 www sermatec ess com 38 Maintenance LED Status...
Страница 39: ...2021 8 19 www sermatec ess com 39 Maintenance Trouble Shooting...
Страница 40: ...2021 8 19 www sermatec ess com 40 Maintenance Trouble Shooting...
Страница 43: ...Thanks...