Section 2: ELECTRICAL INSTALLATION
2. DETERMINE CABLING ARRANGEMENT
a. Figure 11 below shows the entire serial communications link for 2 Operator
Stations. The Terminator must be installed on the Tee Adapter farthest from the
Seakeeper.
FIGURE 11
– CABLING FOR 2 OPERATOR STATIONS
b. The Operator Station nearest the Seakeeper should be connected to CABLE 3.
3. ROUTE 2
ND
OPERATOR STATION CABLE
a. A second CAN Cable Assembly (30243), also a 25 meter shielded cable, and the
largest connector is a molded plug with maximum outer diameter of .58 inch
(14.8mm)).
b. The additional CAN Cable Assembly must be routed in the vessel from the 1
st
Operator Station (female end) to the 2
nd
(male end) Operator Station.
4. INSTALL 2
ND
OPERATOR STATION EQUIPMENT
a. The 2
nd
Operator Station equipment is installed at the determined location using
Electrical Equipment Mounting Instructions in Section 2.1.
5. CONNECT 2
ND
OPERATOR STATION EQUIPMENT
a. The 2
nd
Operator Station equipment is connected in accordance with the Cable
Block Diagram, 90310.