Fig. 13
Z16
Z20
4.25 in
4.56 in
MINIMUN DIMENSION Q
4.2.
Before concreting in the plate insert a flexible plastic duct
into the special hole of the plate.
4.3.
Before concreting in the plate, make sure that it is perfectly
leveled and that the distance of 2,28-2,63 in. as shown in Fig. 13
is respected.
Ø
1.18 in. Minimum
4. FOUNDATION PLATE ANCHORAGE
To install the foundation plate it is necessary to:
4.1.
Prepare a concret basement with the dimensions shown in
Fig. 12 where the foundation plate and the anchor bolts will be
concreted.
NOTE
: It is recommended, gate structure permitting, to lift the
foundation plate about 1.96 in. from the ground, in order to avoid
eventual water stagnation.
1.69-2.28
Fig. 16
6. FITTING OF THE MOTOR REDUCER
6.1.
Insert the 4 grains into the special holes, so that it is
possible to adjust the motor reducer height on the plate (Fig. 15).
At the end of installation check if the 4 crub screws are well
gripped on the foundation plate.
6.2.
Fix the motor reducer to the foundation plate with the 2
included nuts, adjusting the side position (Fig. 16) so to respect
the shown quota in (Fig. 13).
6.3. Remove the closing loading oil cap (red) and substitute
it with that supplied apart provided with the airhole (black).
5
.9
0
16.53
9.84
Plinto
Fig. 12
2.28-2.63
2
.5
5
Max 0.19 in.
5. CABLES PASSAGE ARRANGEMENT
Saturn and Boxer are provided with two different holes for
electric cables passage.
It’s very important to make the high - tension (120V~) cables
pass through one hole and the low - tension cables (24V )
through the other one (Fig. 14)
SATURN-BOXER
MECHANICAL INSTALLATION
67411165
6
International registered trademark n. 2.777.971
Fig. 14
Hole 1
Hole 2
Fig. 15
REV 02 - 12/2013