After the condenser matrix is fully fitted to the mounting surface, hang the cover/fan assembly onto 
its hinges.
With the cover/fan assembly open, connect the wires from the fan to the terminal block .
Note - Ensure that the wiring from the fan is routed through the plastic clip provided to prevent the 
possibility of the wires becoming entangled in the fan blade.

Connect the wiring and the Pipework to the cooler following the instructions supplied with the cooler.

Recommended materials for heat dump to cooler connections.

Pipework - 15mm OD x 10mm ID COBRACOL tubing.
Cable - 1.5 mm sq., 2 core white PVC covered (no earth)
Insulation tubing - 3/8" or 1/2" ID

Use of the equipment.

This unit is intended for use in conjunction with cooling units manufactured by Scotsman
Beverage Systems Ltd.
It is designed to be connected at the end of the water/glycol recirculation lines as a means
of removing heat from the cooling system.
There are 

NO 

other recommended uses for this unit.

DISMANTLING DECOMMISSIONING PROCEDURE

a. Isolate the unit from the Base cooler or Glycol module electricity supply.
b. Disconnect the recirculating coolant inlet and Outlet pipes.

ADJUSTMENTS MAINTENANCE REQUIREMENTS

   

7

Содержание cCool 37FF

Страница 1: ...INSTALLATION AND SERVICE MANUAL 37FF INTEGRAL WATER COOLED SODA CIRCUIT COOLER CARBONATOR CCOOL SODA CIRCUIT COOLER 1...

Страница 2: ...t 6 Connect all products to unit as labelled 7 Connect CO2 gas supply 80psi 90psi to the cooler using the bulkhead fitting labelled CO2 IN 8 Fill the water bath with fresh clean COLD water until the o...

Страница 3: ...IDELINES 1 It is important that the heat dump is sited correctly to enable it to work efficiently The guidelines below should be adhered to wherever possible 2 Ensure the unit is sited on an outside w...

Страница 4: ...n using Cobracol tubing connect the COOLANT OUT from the base unit to the FLOW on the first heat dump Connect the RETURN on heat dump to the FLOW on the second heat dump Connect the RETURN of the seco...

Страница 5: ...inspect for signs of damage Site the dump in a convenient location preferably in a non heat sensitive and shaded areaon the outside of the building If it cannot be installed outside ensure that the a...

Страница 6: ...module and base unit to the fittings on the heat dump labeled FLOW and RETURN and secure the pipes to the mounting surface so that the weight of the pipes is not being carried on the heat dump fitting...

Страница 7: ...heat dump to cooler connections Pipework 15mm OD x 10mm ID COBRACOL tubing Cable 1 5 mm sq 2 core white PVC covered no earth Insulation tubing 3 8 or 1 2 ID Use of the equipment This unit is intended...

Страница 8: ...ny extraneous debris from the unit or its casing preferably using a vacuum cleaner or brush c Check unit for electrical safety POWER ISOLATION METHOD a Switch off the socket that the base cooler unit...

Страница 9: ...noxious gas and as such due care should be taken when handling installing and maintaining the equipment with particular regard to these hazards Carbon Dioxide leaks are potentially fatal if concentrat...

Страница 10: ...required 4 Disconnect all post mix pipework and remove dispense head equipment including the python and remove as recommended by the equipment owner 5 Siphon or pump out water from the waterbath to a...

Страница 11: ...USE OF CARBON DIOXIDE See Carbon Dioxide warning notice at rear of booklet POWER ISOLATION METHOD The unit is wired directly in to the mains electrical supply via an isolator box The recommended isol...

Страница 12: ...nit running for a short period watching out for Leaks Strange noises or any other form of malfunction if no problems are observed then normal operation of the unit may be resumed MAX MIN AMBIENT TEMPE...

Страница 13: ...ect soft drinks CO2 or gas cylinder equipment with other equipment 4 ALWAYS secure cylinder upright whilst in use 5 ALWAYS keep cylinder away from heat 6 NEVER drop or throw cylinders 7 NEVER try to u...

Страница 14: ...E BANK CAPACITY A GUIDE 0 5 10 15 20 25 30 35 0 10 20 30 40 50 60 70 80 90 100 PRODUCT THROUGHPUT LITRES ICE BANK WT KG s DELTA T 5 DEG C DELTA T 10 DEG C DELTA T 15 DEG C DELTA T 20 DEG C DELTA T 25...

Страница 15: ...is working correctly Check the Python lines are clear from blockages there are no kinks and the coils within the bath are not frozen Clear Blockage unkink or replace damaged pipe De ice coils and rect...

Страница 16: ...ket Is the Agitator Motor electrical connector plugged into it s mating socket Is the Agitator Motor running Can the Agitators shaft be rotated by hand Is the unit switched on Agitator motor seized Ag...

Страница 17: ...the compressor does not switch off No Internal wiring fault No Disconnect the probe Is the ice probe sensor covered with ice Does the compressor stop running Reconnect icebank probe System OK Replace...

Страница 18: ...ent temperature 40 C Clean condenser ensure good airflow Yes No Yes Has the unit been subjected to heavy product draw Is the compressor running No Yes Yes Repair refrigerant leak Yes Yes Change Compre...

Страница 19: ...ket Replace fan motor Clean radiator matrix Is the heat dump sited in full sunlight or near other heat sources without adequate ventilation Re site heat dump Is the condenser matrix blocked with debri...

Страница 20: ...col module Is the pump plugged into its mating connector No No Yes Yes Is the glycol level in the header tank between Max and Min marks No Yes No Is the glycol mixture recirculating adequately Yes Are...

Страница 21: ...tallation in general If the python insulation is damaged or considered too thin for the installation it will need to be replaced Check that the python does not exceed the run as statedin the manual fo...

Страница 22: ...Ccool 37FF Mains supply 230 V 50 Hz Amps 17 amps Watts 2620 watts Refrigerant 1450g R134a Water bath 110 litres Ice weight 55 kg Width 1060mm Height 915 mm Depth 720 mm Weight dry 158 kg 22...

Страница 23: ...OR 9 CM46450 32cc COMPRESSOR Ccool 37 Optima 1000 CM47168 Optima 1500 10 MM45034 REFRIGERATION END PANEL 11 MM45035 PUMP END PANEL 12 PI44199 MOTHERBOARD GLOBAL RANGE 13 PI45926 SLAVE BOARD 14 PI44142...

Страница 24: ...1 OP73718 FILLER PLUG 2 OP72094 15mm ACORN ELBOW 3 OP73630 BRASS TAIL 4 PU73602 3 STAGE MAG DRIVE PUMP 5 OP73168 SHUT OFF VALVE 6 OP73326 CHECK VALVE 7 OP74396 TRANSFORMER 8 OP73829 SEALED PLUG 2 WAY...

Страница 25: ...Item No Part Number Description 1 CN42674 3 ROW HEAT DUMP COIL 2 PI42728 IN LINE HINGE 3 OP71769 10 SUCKER FAN BLADE 4 MO46688 25 WATT Q MOTOR EBM 5 PI45861 HEAT DUMP COWL VISION 25...

Страница 26: ...SCOTSMAN BEVERAGE SYSTEMS LTD CHANCEL WAY HALESOWEN INDUSTRIAL PARK HALESOWEN WEST MIDLANDS B62 8SE ENGLAND Tel 44 121 501 2566 Fax 44 550 0873 MANUAL REF WDE INS 90 ISSUE 1 DATE 09 10 01 26...