INSTALLATION INSTRUCTIONS FOR
INTEGRAL & WATER COOLED UNITS
NOTE:
The unit should be installed and serviced by a suitably trained person.
NOTE:
Sealed plugs may be fitted to new units.
1. Unpack the unit from its transportation packing and visually check for any signs of damage.
2. Site the unit in a convenient location in the cellar or room on a level surface where it is to be
located and make sure that a mains electricity supply is within 2 meters and in an area allowing
free circulation of air. The unit should be fitted to the following electrical supply
CCOOL 37 ----- 240v AC 30 amp isolator box installed with a suitable 30 amp circuit
breaker or fuse link.
3.
If the unit is a water cooled version, the glycol module and heat dumps must be installed and
connected as detailed in the
GLYCOL MODULE AND HEAT DUMP INSTALLATION
INSTRUCTIONS
of this manual , before commissioning the complete system.
4. Connect the dispense head to the unit using suitable fittings and python, referring to the
connection diagram on the lid of the cooler and those supplied with the dispense head.
5. Remove the top cover and connect a mains water supply of 50psi / 60psi to the water pump inlet
labelled ‘WATER IN’, at the rear of the unit.
6. Connect all products to unit as labelled.
7.
Connect CO
2
gas supply (80psi - 90psi) to the cooler using the bulkhead fitting labelled ‘CO2 IN’
8.
Fill the water bath with fresh clean
COLD
water until the overflow level is reached.
9. Connect unit to the mains electricity supply (do not turn on yet).
10.
Turn on the CO
2
supply and vent the carbonator bowl using the relief valve located on the top.
Additionally operate the dispense valve until the air in the python system is purged.
11. Turn on the mains water supply.
12. Check for obvious leaks and rectify before proceeding any further.
13. Ensure that the soda recirculation pump is disconnected / switched off.(See switch panel
operation on page 2)
14. Switch on the unit at the mains power supply and allow ice bank to build, the dispense system to
prime and fill with carbonated water and the cooling system to prime. If the carbonator overtime
indicator comes on at any time during this process, reset by operating the carb reset switch.
(see switch panel operation on page 2)
15. If the unit is a water cooled version , ensure that the glycol lines prime correctly and that the
glycol module is topped up to the correct level.
16.
Prime dispense head by operating the valves and ensure all pockets of CO
2
are removed from
system.
17. Reconnect / switch on the soda pump.
18. Operate dispense valves until syrup is dispensed from valves.
19. Refit the top cover to the base unit.
2