LED R&D Lab(VD)
37
⑨
Install the ASSY BRACKET P-FRONT by hanging it on the ASSY BRACKET P-FRAME..
- After installing 1st and 2nd in the middle, install them in order of 3rd and 4th.
- Be sure to comply with the installation order
- Since it is installed on hanging, it is raised and installed at an angle.
-
The numbers L1, L2, R1, and R2 of each cabinet are arranged as shown in Figure 1.
Fig.1
Install position 1 first
Fig.2
Up and down at an angle
1
2
3
4
L1
L2
R1
R2
4. FRAME installation and cable connection
Содержание IAB Series
Страница 1: ...LED R D Lab VD LED Display Install Manual IAB Series LH008IAB LH012IAB LH016IAB Ver 1 4 ...
Страница 25: ...146 ...
Страница 48: ...110 ...
Страница 67: ...146 ...
Страница 72: ...110 ...
Страница 90: ...Thank you ...
Страница 115: ...LED R D Lab VD 114 Product disassembly method 3 Sub Screen Internal decomposition First fully connected state ...
Страница 122: ...LED R D Lab VD 121 First fully connected state Product disassembly method 3 Sub Screen Internal decomposition ...