EB 8384-2 EN
63
Start-up and settings
7 Start-up and settings
Risk of malfunction due to incorrect sequence
of mounting, installation, and start-up.
Keep the following sequence.
1. Remove the protective film from the pneu-
matic connections.
2.
Mount the positioner on the control valve.
3. Connect the supply air.
4. Connect the electrical power.
5.
Perform the start-up settings.
Reading after connecting the electrical pow-
er supply:
tEStinG
runs across the display and the
fault alarm icon appears and blinks on the
display when the
positioner has not been
initialized
. The reading indicates the lever
position in degrees in relation to the mid-ax
-
is.
Reading when the positioner
has not yet been initialized
Code 0 is displayed when a
positioner has
been initialized
. The positioner is in the last
active operating mode.
Risk of injury due to the actuator stem ex-
tending or retracting.
Do not touch or block the actuator stem.
The positioner performs a test in the start-up
phase while following its automation task at
the same time.
During the start-up phase, operation on site
is unrestricted, yet write access is limited.
Perform the start-up settings in the same se-
quence as described (section 7.1 to sec
-
tion 7.6).
7.1
Defining the fail-safe posi
-
tion
Define the fail-safe position of the valve
(0 %) taking the valve type and the actua
-
tor's direction of action into account. Position
the AIR TO OPEN/AIR TO CLOSE slide
switch accordingly:
−
AIR TO OPEN
setting
Signal pressure opens the valve, e.g. for
a fail-close valve
The AIR TO OPEN setting always applies to
double-acting actuators.
−
AIR TO CLOSE
setting
Signal pressure closes the valve, e.g. for
a fail-open valve
For checking purposes:
after successfully
completing initialization, the positioner dis
-
play must read 0 % when the valve is closed
and 100 % when the valve is open. If this is
not the case, change the slide switch position
and re-initialize the positioner.
NOTICE
!
WARNING
!
Note
Содержание 3730-2
Страница 19: ...EB 8384 2 EN 19 Design and principle of operation...
Страница 109: ...EB 8384 2 EN 109...
Страница 110: ...110 EB 8384 2 EN...
Страница 111: ...EB 8384 2 EN 111...
Страница 112: ...112 EB 8384 2 EN...
Страница 113: ...EB 8384 2 EN 113...
Страница 114: ...114 EB 8384 2 EN...
Страница 115: ...EB 8384 2 EN 115...
Страница 116: ...116 EB 8384 2 EN...
Страница 117: ...EB 8384 2 EN 117...
Страница 118: ...118 EB 8384 2 EN...
Страница 119: ...EB 8384 2 EN 119...
Страница 120: ...120 EB 8384 2 EN...
Страница 121: ...EB 8384 2 EN 121...
Страница 122: ...122 EB 8384 2 EN...
Страница 123: ...EB 8384 2 EN 123...
Страница 124: ...124 EB 8384 2 EN...
Страница 125: ...EB 8384 2 EN 125...