Car lift installation, operation and maintenance manual Type
:
4SF-4000B
7
Packing dimension drawing
3.2 Precautions during installation
▲
During installation, please observe that the two upright columns are parallel and vertical to the ground, and shall not be tilted.
▲
hydraulic hose and steel cable connection, the joint must be connected in place, so as to avoid oil leakage and steel cable loose.
▲
All bolts and nuts must be tightened to ensure fastening.
▲
No vehicles shall be placed during the test.
3.3 Installation steps
Step 1
:
Choose the suitable place
:
The lift is for indoor use only. It is installed on strong concrete, not installed on the expansion joint of the cement ground, and shall not be installed
on the ground floor of the two or high floor without the permission of the relevant building personnel.
Step 2
:
Determine the installation position and lift the hoist to the installation site with a crane.
Note: The four post car lift has three pieces of goods:1 piece of power unit, 1 piece rolling jack and
1 piece machine package
Step 3
:
Remove the "power unit" to the free place
Step 4
:
Remove the
"rolling jack" in the free place with the lifting device
Step 5
:
Disassembly package
<1>
:
The pre placed wood on the ground (wood thickness greater than 120mm), crane for packaging side below the bridge plate is placed on wood,
the purpose is to let off the ground at the bottom of the packing frame.