ATTENTION - DANGER
NEVER ACTIVATE THE RISING BOLLARD
BEFORE HAVING FIXED THE TREADABLE
FLANGE!
15 -
When the bollard is lowered, take out the blocks on the pipe guide
ring and place the treadable flange.
With the treadable flange check the final level with respect to the external
floor.
Insert the washers and the M8x35 TSEI stainless steel screws.
Carry out the electrical connection carefully following the diagram supplied
with the control unit. See figures alongside.
14 - Verify that the distance between the bollard flange and the upper edge
of the case/flooring is equal to 23-24 mm.
By respecting this distance the treadable flange will be slightly raised com-
pared (1/2mm) to the flooring, limiting the amount of dirt that may infiltrate
the inside of the bollard.
In an effort to reduce possible infiltrations, if the flooring allows it, plan on
a slight slope around the foundation case.
See figures alongside.
13 - After positioning the bollard inside the case, remove the lifting
eye¬bolts and, using the same holes, position the blocks on the pipe
guide ring.
The blocks are necessary in order to lift the bollard without the treadable
flange.
Insert the M10x40 TCEI stainless steel screws partially with the relevant
washers into the four holes Ø13, without screwing them completely, in
order to regulate the planarity of the bollard through the adjustable sup-
ports.
Connect the bollard to the control unit and then lift it electrically. Refer to
instructions supplied with the control unit.
With the bollard completely lifted, adjust its level. Completing this adjust-
ment with the bollard lifted makes it possible to verify, even visually, that
the cylinder is perfectly vertical, a necessary condition for the automation
to operate properly.
See figure alongside.
1/2 mm
23/24 mm
M10x40 TCEI
20-22