20
P
OWER
C
ONNECTION
ALL CHECK ON THE DATA PLATE THAT THE VOLTAGE OF THE BATTERY PACK IS THE SAME AS
THAT ALLOWED BY THE UPS.
W
IRE
C
ONNECTION
Installation and wiring must be performed in accordance with the local electric laws/regulations and execute the following
instructions by professional person.
1) Make sure the mains wire and breakers in the building are enough for the rated capacity of UPS to avoid the
hazards of electric shock or fire.
NOTE: Do not use the wall receptacle as the input power source for the UPS, as its rated current is less than the UPS’s
maximum input current. Otherwise the receptacle may be burned and destroyed.
2) Switch off the mains switch in the building before installation.
3) Turn off all the connected devices before connecting to the UPS.
4) Prepare wires based on the following table:
Model
Wiring spec (AWG)
Input
Output
Battery
Ground
CSDH6K0GA3
6
6
8
6
CSDHK10GA5
4
4
8
4
NOTE 1
: The cable for CSDH6K0GA3 should be able to withstand over 40A current. It is recommended to use
6AWG or thicker wire for safety and efficiency.
NOTE 2
: The cable for CSDHK10GA5 should be able to withstand over 63A current. It is recommended to use
4AWG or thicker wire for safety and efficiency.
NOTE 3
: The selections for color of wires should be followed by the local electrical laws and regulations.
The following terminal block diagrams:
Connect the ground first when making wire connection. Disconnect the earth wire last when making wire disconnection!
Terminal block wiring diagram of the UPS
Содержание Sentinel RT 10000 VA ER
Страница 1: ...User Operations Manual Sentinel RT True Online UPS System 6000 VA 6000 VA ER 10000 VA 10000 VA ER ...
Страница 2: ......
Страница 41: ......
Страница 42: ...0MLSDH6K0RUENUA ...