5 Maintenance
5-3
5.1 What to take into account
(continued)
The following steps must be carried out after completing the
work:
Step
Operation
1
Follow the maintenance schedule and complete the
inspection sheets, activity logs, etc. (see Appendix W
“Maintenance Check”).
2
Check that the safety devices are working correctly.
Do not release the machine for operation if the safety
devices are not in perfect working order.
3
Reinstall and secure any safety devices that have
been removed.
4
Remove any tools, foreign objects and materials left
lying around.
5
Carry out a test run and check the function of the ser-
viced components.
6
If you leave the machine before completing the work
keep the keys safe and inaccessible to unauthorised
persons.
Only genuine spare parts should be used when replacing com-
ponents such as the oil filter, oil, air filter, separator cartridge, V-
belt, etc.
Only allow authorised dealers to carry out repair work.
A list of other persons authorised by the manufacturer to carry
out repairs can be obtained from the manufacturer on request.
Do not allow repairs to be carried out by any persons other
than those authorised by the manufacturer!
Servicing is carried out as agreed with the authorised dealer.
After completion of
work
Spare parts,
accessories
Repairs