Unit Assembly Prior to Installation
After the framing has been built, the nail-
ing Flanges will need to be set depending
on the depth of finishing material being
used. Up to 1-1/4” total material thickness
can be used, including the backing mate-
rial. The depth of finishing material can be
adjusted in 1/4” increments.
1-1/4”
Finishing
Material
Depth
Flush
Setting
1. Determine the required depth set-
ting for the materials being used.
2. Once the setting has been chosen,
install the Left and Right Nailing
Flanges with 2 screws on each
Flange.
1”
3/4”
1/2”
1/4”
Front of Fireplace
Nailing Flange Parts
Top Nailing Flange
Standoff Deflector
Left Nailing Flange
Right Nailing Flange