G-Series Installation & Commissioning
70
6.1
Power up test
It is advisable to perform an initial power-up test to help ensure that
the system is wired correctly.
Perform the following initial checks before proceeding to the com-
missioning stage:
Turn on breakers
Turn on the power to the equipment at the distribution panel:
1. Monitors and ancillary equipment.
2. GPM400 processors.
Power up sequence
Power up the monitors first to allow the boot sequence and start-up
information to be shown at master monitors.
Check system:
Wait for 2 minutes whilst the boot sequence is completed, then
check each of the following:
•
Monitors
•
Keyboards
•
GPM400 processors
•
GVM400 Video Modules
•
SeaTalk
hs
Switch
•
DSM sounder module. (refer to separate instructions supplied
with the DSM)
Marine monitor checks
You will need to select the appropriate input on each monitor.
On a G-Series marine monitor:
•
Press the power key (if required)
•
Press the Left/Right arrow keys to scroll through the inputs.
On a healthy system all monitors will:
•
show the G-Series set-up wizard screen on the appropriate in-
put channel.
Note:
Only the master monitors will show the initial boot
sequence. The repeat monitors may not begin to operate
until the system has ran through its start-up sequence
(approximately 2 minutes after power on).
Keyboard checks
You can check that each keyboard is correctly connected by look-
ing at its LCD monitor.
On a healthy system all keyboards will:
•
Display the message “NOT ASSIGNED”.
GPM400 processor checks
Check that each GPM is correctly connected by looking at its LED
(found next to the SeaTalk/alarm output).
On a healthy GPM400:
•
LED will flash Green.
For a full LED status listing see
page 99
.
GVM400 video processor checks
Check that each GPM is correctly connected by looking at its LED
(found next to the SeaTalk/alarm output).
On a healthy GVM400:
•
LED will flash Green.
For a full LED status listing see
page 100
.
SeaTalk
hs
switch
Use this to check the status of your SeaTalk
hs
network connections.
Содержание G-Series system
Страница 1: ...G Series Systems Installation and Commissioning Instructions...
Страница 2: ......
Страница 3: ...G Series System Installation Commissioning Instructions Document Number 87070_1 Date June 2007...
Страница 6: ...G Series Installation Commissioning 6...
Страница 10: ...G Series Installation Commissioning 10...
Страница 14: ...G Series Installation Commissioning 14...
Страница 29: ...29 Chapter 3 Packs and contents 3 7 Alarm buzzer Pack items Description Part No Alarm buzzer E26033 D10363 1...
Страница 30: ...G Series Installation Commissioning 30...
Страница 56: ...G Series Installation Commissioning 56...
Страница 68: ...G Series Installation Commissioning 68...
Страница 72: ...G Series Installation Commissioning 72...
Страница 80: ...G Series Installation Commissioning 80...
Страница 102: ...G Series Installation Commissioning 102...
Страница 108: ...G Series Installation Commissioning 108...
Страница 120: ...G Series Installation Commissioning 120...
Страница 126: ...G Series Installation Commissioning 126...
Страница 127: ......