Location

The appliance must be installed on a solid level floor or base 

of incombustible material which is capable of supporting the 

total weight.
The location chosen for the appliance must permit 

installation and the provision of a satisfactory flue and an 

adequate air supply. The location must also provide space for 

servicing and air circulation around the appliance.
Between wall and LH side of appliance 

10mm Between 

wall and RH side of appliance 

 

10mm*

*SHOULD THE WALL PROJECT BEYOND THE FRONT OF 

THE APPLIANCE, WHEN IT MUST BE INCREASED TO 50MM 

(SEE FIG. Fig. 1.1, Fig. 1.2).*

Above the raised insulating cover handle  60mm

NOTE: GAS AND WATER CONNECTIONS ARE LOCATED 

ON THE LH SIDE OF THE APPLIANCE. INSTALLERS MUST 

MAKE PROVISION FOR ACCESS TO THESE CONNECTIONS 

DURING INSTALLATION.

In addition, adequate clearance must be available at the 

front of the appliance to enable it to be operated and 

serviced. Flue pipes and fittings must not be closer than 

25mm to combustible materials and where passing through 

a combustible partition such as a ceiling or roof, must be 

enclosed in a non-combustible sleeve providing an air space 

of at least 25mm.
Spaces around flue pipes passing through walls or floors 

should be sealed against the passage of smoke and flame.

Where the cooker is to stand in a recess or against a wall 

which is to be tiled, 

in no circumstances should the tiles 

overlap the cooker top plate.
NOTE: SMOKE/SMELL EMITTED DURING INITIAL USAGE.

Some parts of the cooker have been coated with a light 

covering of protective oil. During initial operation of the 

cooker, this may cause smoke/smell to be emitted and is 

normal and not a fault with the appliance, it is therefore 

advisable to open doors and or windows to allow for 

ventilation. Lift the insulating lids to prevent staining the 

linings.

Gas supply

Pipework from the meter to the appliance must be of 

adequate size. It is recommended that ø22mm minimum 

diameter copper tubing is used. Do not use pipes of a smaller 

size than the appliance gas connection. The complete 

installation must be tested for soundness and purged in 

accordance with the regulations in force.

Electrical supply

External wiring must be correctly earthed, polarised and 

in accordance with current regulations. The main supply 

required is 230V, 50Hz fused at 3A.

NOTE

: The method of connection to the electricity supply 

must facilitate complete electrical isolation of the appliance, 

preferably by the use of a fused three pin plug and 

unswitched shuttered outlet. Alternatively, connection may 

be made by a via a fused double-pole isolator with a contact 

separation of at least 3mm in all poles and serving the 

appliance and system control only.

Site Requirements

Содержание Heatranger 480AG CF

Страница 1: ...e mask and disposable gloves Glass Yarn Mineral Wool Insulation Pads Ceramic Fibre Kerosene Oil may be harmful if inhaled may be irritating to skin eyes nose and throat When handling avoid inhaling an...

Страница 2: ...13 Main burner lighting 14 Spillage test 14 Servicing 15 Annual servicing 15 Service schedule 15 Pre service check 15 Hotplate cleaning 15 Burner access 15 Burner cleaning 16 Heat exchanger 18 Combust...

Страница 3: ...rner pressure Min Boiler Output 17 6kW at 8mbar burner pressure 480AL PROPANE G31 TOTAL BOILER COOKER MIN MAX MIN MAX Max Heat Inputs Gross 35 8kW 40 7kW 25 6kW 30 5kW 10 2kW Max Heat Inputs Net 33 0k...

Страница 4: ...ke and flame Where the cooker is to stand in a recess or against a wall which is to be tiled in no circumstances should the tiles overlap the cooker top plate NOTE SMOKE SMELL EMITTED DURING INITIAL U...

Страница 5: ...LER MUST MAKE PROVISION TO GAIN ACCESS TO 22mm COPPER FLOW AND RETURN PIPE DURING INSTALLATION R 1 2 1 2 BSP TAPER 10mm 10mm 50mm MINIMUM GAP ON RIGHT HAND SIDE MINIMUM GAP ON LEFT HAND SIDE WALL PROJ...

Страница 6: ...ipe constructed in a to c above should form the initial connection to lined chimneys Where a chimney is to be used which is not composed of or lined with a non porous acid resistant material it should...

Страница 7: ...e pipes should rise upwards in the direction away from the appliance Circulating Pump It is recommended that the selected pump be sized to suit the boiler pressure loss see Fig 1 3 and therefore adequ...

Страница 8: ...lowing items which are supplied separately packed and require assembly 1 Draught Diverter Assembly See Fig 1 4 2 Appliance Rear Distance Bracket for use when appliance is installed 25mm away from a re...

Страница 9: ...take the weight of the appliance on the crowbar and remove the rear rolled tube followed by similar action on the front tube 2 Assemble and locate the flue draught diverter assembly on flue spigot as...

Страница 10: ...ed so that it is operated on demand only Operation of the system under control of the boiler thermostat only does not produce the best efficiency Refer to the control equipment manufacturer s literatu...

Страница 11: ...ive MUST be connected to the terminal marked BSL NOTE The link between terminals L1 and BSL MUST be removed to ensure correct operation of the time switch If the time switch is fitted to the cooker th...

Страница 12: ...INK L1 TO CSL OR PROVIDE TIMED LIVE FOR COOKER BURNER LINK L1 TO BSL OR PROVIDE LIVE SUPPLY TO BOILER FROM PROGRAMMER OR AUXILIARY CONTROLS G Y G Y G Y G Y WH BL Y 9 8 7 3 G Y BR BR BL BR BR OR OR BL...

Страница 13: ...ighting the pilot Boiler see Fig 1 14 This appliance is fitted with an automatic ignition unit that will light the main burner on demand Should button K see Fig 1 14 be illuminated press button this w...

Страница 14: ...k the system for leaks When all the air has been removed from the water circuit the pump and radiators should be balanced to achieve the correct temperature to drop across the system Set any timer roo...

Страница 15: ...rs 5 Clean the heat exchanger 6 Check the condition of the boiler combustion chamber insulation 7 Check that the flueway is unobstructed and that the draught diverter unit is correctly assembled 8 Ove...

Страница 16: ...Fig 1 18 Brush the boiler burner top and check the flame ports are clear Any deposits may be removed with a non metallic brush Remove three screws securing burner assembly to manifold A Remove two sc...

Страница 17: ...ing injector bracket and remove controls away from burner door Brush burner venturi and remove any deposits from inside the burner venturi and tip downwards to discharge debris Remove the burner injec...

Страница 18: ...access plate See Fig 1 24 Remove access plate R Using a suitable brush clean the heat exchanger from above and below NOTE The insulation used on the inside surface of the combustion chamber is delica...

Страница 19: ...ON Following the sequence in COMMISSIONING INSTRUCTIONS To fit new burner Follow instructions in section Burner Cleaning of Servicing Instructions and remove the cooker burner assembly 1 Remove two p...

Страница 20: ...rmostat control knobs 3 Remove the 2 cover panel fixing screws 4 Remove cover panel SEE Fig 1 26 5 Remove the two control panel fixing screws 6 Tilt the chassis from the top and lift out taking care n...

Страница 21: ...thermostat capillaries 9 Re assemble in reverse order To fit new cooker overheat See Fig 1 27 AND Fig 1 28 Follow instructions in ELECTRICAL COMPONENT ACCESS Steps 1 to 6 1 Undo the two screws on the...

Страница 22: ...or 3 Fit replacement 4 Re assemble in reverse order 5 Check for gas soundness To fit new burner Follow instructions in section Burner cleaning Instructions and remove the boiler burner assembly 1 Remo...

Страница 23: ...spindle locknut and extract overheat thermostat 5 Fit replacement thermostat 6 Re assemble in reverse order To fit combustion discharge safety device SEE Fig 1 33 Fig 1 34 1 Remove CDSD phial from sp...

Страница 24: ...er or return side of all heat emitters or radiators b Where access to a make up vessel would be difficult by a remote automatic pressurisation and make up unit c Mains Connection There shall be no con...

Страница 25: ...LTERNATIVELY THE BYPASS LOOP CAN INCORPORATE A TOWEL RAIL CONTROLLED BY A NON ADJUSTABLE BALANCING VALVE SHOULD THE PUMP BE FITTED TO THE RETURN THEN THE PRESSURE GAUGE AND EXPANSION VESSEL ARE FITTED...

Страница 26: ...change specifications and make modifications to the appliances described and illustrated at any time www agaliving com www agacookshop co uk Manufactured By AGA Rangemaster Station Road Ketley Telfor...

Отзывы: