Quadnet Installation Instructions 

  

 

 

 

 

Loop Loading 
 

In  order  to  allow  a  method  of  calculating  the  maximum  loop  loading  that  the  system  will  support,  each 
device has a rating assigned in Alarm Loading Units (ALUs). A maximum of 175 ALU are permissible on 
the loop. This only relates to the load presented in alarm and does not necessarily affect an input device. 
 
The  Quadnet  OSP  programming  software  automatically  keeps  control  of  the  quantity  and  will  provide 
prompts if the limits are reached. 
 

DESCRIPTION 

ALU RATING 

Sounder Low 

0.5 

Sounder Medium 

Sounder High 

Beacon 

Loop I/O Module 

Conventional Zone Module: Powered from loop 

10 

Conventional Zone Module: Powered remotely 

  
Note:  Whilst  the  system  will  operate  a  maximum  of  800  devices  per  control  panel,  for  compliance  with 
EN54: Part 2: 1997 Amendments 1 and 2, it is recommended that a limit of a maximum of 512 detection 
devices  is  adhered  to.  This  includes  detectors  and  manual  call  points,  but does not affect the number of 
sounders or other alarm devices on the system. 

Содержание Quadnet

Страница 1: ...26 0903 Issue 1 Fire Detection Alarm System Control Panel V1 000 INSTALLATION INSTRUCTIONS TO BE RETAINED BY THE INSTALLATION ENGINEER...

Страница 2: ...pect of such contents Due to the complexity and inherent importance of a life risk type system then training on this equipment is essential and commissioning should only be carried out by competent pe...

Страница 3: ...Batteries 15 PSU Termination Schematic 26 Network 17 Topology and Cable Specification 17 Network Connection Schematic 18 Commissioning 19 Installation 1 st Stage 19 Installation 2 nd Stage 19 Commiss...

Страница 4: ...warranty unless the system is installed commissioned and serviced in accordance with this manual and the relevant standards by a suitably qualified and competent person or organisation Anti Static Ha...

Страница 5: ...ntelligence signifies that the signal processing is spread throughout the system in order that the decisions about fires and faults are taken within the detector itself The detector is capable of bein...

Страница 6: ...ocate the control panel where extremes of temperature or humidity may occur or where there is any possibility of condensation or water ingress Like all electronic equipment the control panel may be af...

Страница 7: ...lation Instructions 7 Cabinet Installation The four mounting holes in the back box should be used to secure the cabinet to a solid wall using suitable screws of at least 50mm in length Physical Dimens...

Страница 8: ...nections must be installed with a maximum length of 500m between network ports The Power Supply Unit requires both a data connection and dual power connections Thus one x 2 core 1 5 mm 2 screened fire...

Страница 9: ...control of the quantity and will provide prompts if the limits are reached DESCRIPTION ALU RATING Sounder Low 0 5 Sounder Medium 1 Sounder High 2 Beacon 1 Loop I O Module 1 Conventional Zone Module P...

Страница 10: ...2 X 2C2 5 QUADNET CONTROL PANEL QUADNET PSU 1 X 2C1 5 2 X 2C2 5 ADDRESSABLE LOOPS ALL 2C1 5 ADDRESSABLE LOOPS ALL 2C1 5 ADDRESSABLE LOOPS ALL 2C1 5 NETWORK 2C1 5 QUADNET PSU OPTIONAL UP TO 4 MAX PER...

Страница 11: ...Quadnet Installation Instructions 11 Addressable Circuit Loops 1 4 END1 END 1 SCRN END2 END2 SCRN END1 END1 MI SCREEN ON BOARD PCB FIELD CONNECTIONS SCREEN END2 MI END2 SCREEN SCREEN...

Страница 12: ...urn due to the possibility of data corruption Addressable spur radial circuits may be connected from any multipoint detector but not from any other device Devices covering a maximum of 1 zone per spur...

Страница 13: ...Instructions 13 Power Supply Unit General Assembly Cabinet Installation The four back plate holes should be used to secure the cabinet to a solid wall using suitable screws of at least 50mm in length...

Страница 14: ...Quadnet Installation Instructions 14 Physical Dimensions 50mm 50mm...

Страница 15: ...the connection leads supplied We recommend the use of type Yuasa NP3 2 12 FR or other equivalent approved type Note that batteries are electrically live at all times and great care should be taken to...

Страница 16: ...S BAT BAT 24V FUSE1 BATTERY 10A T QUADNET PSU CONTROLLER EARTH LEAD SCRN B A SCRN OV 24V SCRN OV 24V INPUT CONNECTORS ENSURE THAT THE INCOMING EARTH CABLE IS CONNECTED DIRECTLY TO THE EARTH STUD IN TH...

Страница 17: ...n A cable complying with the BS 5839 Pt1 2002 Amendment 2 2008 Category 1 cables required to operate for prolonged periods during fire conditions is required This must be a 2 core 1 5mm 2 screened fir...

Страница 18: ...Quadnet Installation Instructions 18 Network Schematic All network cables should be 2 core 1 5mm2 screened and fire rated NETWORK RING PANEL 001 PANEL 002 PANEL 003 PANEL 004 PANEL 005 PANEL 006...

Страница 19: ...equired for general electrical installations The control panel back box should be mounted with the mains supply tested connected and isolated at the un switched fused spur ready for the commissioning...

Страница 20: ...ription Ground Floor DEVICE ADDRESS SERIAL NUMBER DEVICE DESCRIPTION 24 CHARACTERS MAX ZONE DEVICE TYPE SMOKE MODE HEAT MODE ALARM CONF N 1 212 Shop Floor Main Entrance 1 MCP 2 30960 Staff Area Rear L...

Страница 21: ...em Controls Event log 1000 events Inputs and Outputs Relay Outputs x 4 Monitored Outputs Monitored Inputs volt free contacts SPCO 30vDC 2A max volt free contacts SPCO 2 x 24v conventional monitored ou...

Страница 22: ...nd at one end will be spaced further apart than the others The resistor should be viewed with this band to the right as follows reading from the left and side of the resistor Band 4 Band Codes 5 Band...

Страница 23: ...y clipped or in containment All loop bases and back boxes installed and terminated All devices have positive core links in place Loop insulation and continuity testing complete and form filled out As...

Страница 24: ...tery etc cleared from control panel Correct operation and device poll verified using SitaDIAGNOSTIC Step 2 Description Commissioning Engineer Checked Data Uploaded to PC Configuration set up on pc Dat...

Страница 25: ...ion the system CONTINUITY READING OHMS CORE LOOP 1 LOOP 2 LOOP 3 LOOP 4 LE1 ve to LE2 ve LE1 ve to LE2 ve LE1 Scrn to LE2 Earth A reading of approximately 1 ohm per 100 meters of 1 5 mm 2 cable is exp...

Страница 26: ...2 ve to ve with temp short circuit applied ve to Earth with temp short circuit applied ve to Earth with temp short circuit applied A reading of approximately 1 ohm per 100 meters of 1 5 mm 2 cable is...

Страница 27: ...e system CONTINUITY READING OHMS CORE Main Ring ve to ve ve to ve Screen to Screen A reading of approximately 1 ohm per 100 meters of 1 5 mm 2 cable is expected and any significant variation from this...

Страница 28: ...E DETAILS CONTROL PANEL NO DESCRIPTION LOOP NO DESCRIPTION DEVICE ADDRESS SERIAL NUMBER DEVICE DESCRIPTION ZONE DEVICE TYPE SMOKE MODE HEAT MODE ALARM CONF N Eg 1 35415 Gnd Flr Front Office 1 MPWS SM2...

Страница 29: ...Quadnet Installation Instructions 29 Your Notes...

Страница 30: ...Quadnet Installation Instructions 30 Your Notes...

Страница 31: ...Quadnet Installation Instructions 31 Your Notes...

Страница 32: ...panel with radial spur circuits only from Multipoint detectors Make sure that the screen cables are sleeved connected together and connected to earth only at the control panel The commissioning engin...

Отзывы: