Valve Operation
Startup
1.
Install the valve pneumatically as shown in Section 1.5 and set the air
pressure that operates the valve between 60-100 psi.
2.
Cycle the valve several times. Make sure that the valve is not pointed at
anyone.
When the valve cycles correctly, you can hear the piston hit the stroke adjustment
screw and the rods can be seen going up and down in the center.
NOTE: If the valve does not cycle correctly, refer to Section 11.
3.
Connect the material delivery system to the valve. Part A material
connects on the on the left side, part B material connects on the right side.
4.
Cycle the valve open to bleed. Part A and B materials should start to
flow separately out of the fluid manifold.
5.
Bleed the valve until all the air is released, and the material releases
smoothly without any breaks in the flow. Any break in the flow of the
material shows there is still air in the system.
6.
Bleed air from the bleed screws if necessary.
NOTE: Part A and B materials may not start to dispense from the valve at
the same time, flow depends on the necessary mix ratio.
7.
Use a 3/16” hex key to adjust the stroke adjustment screw to get the
necessary amount of snuff back.
Turn the stroke adjustment screw clockwise to decrease the amount of snuff back,
or counter-clockwise to increase the amount of snuff back. If the stroke adjustment
screw is turned down too far the valve will not close and material will leak from the
manifold nozzle.
NOTE: A good general setting for snuff back is to turn the stroke
adjustment screw clockwise until material starts to leak from the valve
manifold when under pressure, then turn the stroke adjustment screw a ½
turn counter-clockwise or until it does not leak.
8.
When snuff back is set, use an adjustable wrench to tighten the jam nut
against the sealing washer and cylinder cap to lock it in place.
NOTE: Refer to Section 11 for any other problems.
Содержание PC200 Series
Страница 37: ...PC200 PVA Revision G 2019 37 of 56 PC200R Series Mechanical Drawings Figure 59 Mechanical Drawings PC200R ...
Страница 41: ...PC200 PVA Revision G 2019 41 of 56 PC200RW Series Mechanical Drawings ...
Страница 43: ...PC200 PVA Revision G 2019 43 of 56 How to Order Figure 63 Part Number Configuration ...
Страница 45: ...PC200 PVA Revision G 2019 45 of 56 Figure 64 Accessories and Options ...
Страница 53: ...PC200 PVA Revision G 2019 53 of 56 Notes ...