EmpyrE ElItE InstallatIOn and OpEratIOn manual 

17

operaTIon

Understanding the Gasification Process of 

the Empyre Elite Wood Furnace

Wood  gasification  is  an  amazingly  clean  burning  and 

efficient  process!  It  is  a  process  where  much  of  the 

solid fuel is converted to gases. These gases ignite 

and burn along with the solid fuel. A large percentage 

of wood is converted into gases. In order to burn these 

gases there must be the right amount of air, as well as 

temperatures of well over 1000ºF (538ºC). Gasification 

is accomplished in the Empyre Elite furnace because:

a) air flow is engineered to provide the correct amount of 

under fire and over fire air. This setting is calibrated for 

burning seasoned wood;
b) temperatures high enough to burn the gases are 

reached in the insulated chamber below the firewood.
A key factor in the gasification process is the wood itself, 

the type of wood, the moisture content, diameter, length 

and placement in the firebox. The Empyre Elite furnace 

is not difficult to operate using seasoned wood and by 

using the following guide it will also work well even when 

using less than ideal wood.
The gases in the wood are released when the wood 

surface is exposed to the fire. The more surface area of 

a piece of wood that is exposed and the drier the wood 

is, the faster the gases are released. Example: A small 

DRY piece of burning firewood will release gases much 

faster than a large WET piece of firewood.

Scenario 1: in the case of the small DRY piece of 

firewood which has a lot of exposed surface area, the 

gases are released rapidly and the fire burns very hot 

but it is starving for air due to the high volume of gases. 

This will eventually create smoke.

Scenario 2: in the case of the large piece of WET firewood 

that, in proportion to its mass, has little surface area 

and will release gases slowly. In this case there is too 

much air. The air is now cooling the fire resulting in blue 

smoke and very little heat.
Generally speaking, when burning extremely dry 

firewood,  pieces  should  be  over  5”  (12.7  cm)  in 

diameter. If using high moisture wood, use pieces that 

are less than 5” (12.7 cm) in diameter. It is good to mix 

the dry and wet wood when possible. When using the 

recommended seasoned wood, where the moisture 

content is between 19% and 25%, the diameter of the 

wood is not that important.

Scenario  1  is  also  created  when  stirring  a  hot  fire. 

Scenario 2 is also created when firewood is too short 

in relation to the length of the firebox. Correct length of 

firewood for the Empyre Elite 100 is 18” - 25” (45.7 cm - 

63.5 cm), the Elite 200 is 20” - 28” (50.8 cm - 71.2 cm).
Stack wood pieces side by side. If pieces are short 

place them end to end making one long piece. Firewood 

should be centered front to back over the brick slots.
Scenario 2 is also created when wood bridges in the 

firebox. This is often due to wood with high moisture 

or lack of careful placement of the wood. Scenario 2 

is also created when starting up a cold furnace. Only 

a small amount of wood is burning with a lot of excess 

air.

Identifying smoke Verses Condensation

Mostly the exhaust from the chimney will be clear. There are 

times soon after loading the furnace when a gray vapour 

may appear. This vapour disappears soon after leaving the 

chimney. This vapour is moisture being released from the 

wood. Smoke is more blue in colour and will not disappear 

as quickly as the gray vapour. On a cold winter day what 

looks like smoke may only be vapour.

loading Wood into the Firebox

1.  The right time to add wood is when there still is a good 

layer of charcoal or wood left, but not so much that it 

is difficult to stir.

2.  Using the ash rake, gently pull the charcoal away from 

the back of the firebox. Stir the charcoal sufficiently 

so that ash falls down through the brick slots. Always 

ensure that the brick slots are not blocked by ash 

buildup. Place wood into the firebox, DO NOT throw, as 

this may damage the brick lining.

Correct:

The firebox should be loaded with 

wood of proper length. This will 

lengthen the burn time.

Incorrect:

The firebox loosely filled with irreg

-

ular pieces of wood will decrease 

burn time and may cause unneces-

sary bridging.

Содержание Empyre Elite 100

Страница 1: ...Installation and Operation Instructions Empyre Elite Model 100 and 200...

Страница 2: ......

Страница 3: ...stallation 10 Supplying Make Up Air 11 Low Water Temperature Protection 11 Empyre System Optimizer 11 Electrical Hookup 12 Water Line Hookup 12 Side Arm Installation 14 Optional Heat Exchanger 14 Auxi...

Страница 4: ...Switch DTS 22 Hot Water Wood Furnace Wiring Diagram 23 How to Correct a Sticking Flapper 24 Furnace Specifications 25 Furnace Options 25 Ash Rake and Brush Hanger Assembly 25 Unit Dimensions Model 100...

Страница 5: ...ed wood gasification to produce highly efficient combustion in the furnace s dual burn chambers 1 Wood in the firebox burns from the bottom up drying the top layer of wood in the firebox and forcing g...

Страница 6: ...ax Combustion Blowers Empyre Elite 100 70211231 Fuel Burn wood only Floor May be installed on a well constructed combustible floor A noncombustible liner must be placed underneath the furnace at least...

Страница 7: ...OOR ALWAYS OPEN SLOWLY 1 ALWAYS switch furnace off before opening door DO NOT operate with ash removal door open 2 CLOSE and LATCH door firmly CAUTION Keep children a safe distance from the furnace DO...

Страница 8: ...lly hazardous situation that if not avoided MAY result in minor or moderate injury if proper practices are not taken or serves as a reminder to follow appropriate safety practices Safety Decals Please...

Страница 9: ...Empyre Elite Installation and Operation Manual 7 Safety 1 3 4 5 7 6 Front View 1 2 3 Rear View 6 4 5 7 2...

Страница 10: ...Operation Manual Features Identifying Main Components see list of components on page 9 47 46 45 48 1 10 12 9 8 7 6 5 4 3 2 11 42 43 41 40 39 38 44 26 27 14 13 28 29 30 16 15 19 17 18 31 21 22 23 25 1...

Страница 11: ...urnace 12 305 mm Front of Furnace to Combustibles 48 1220 mm Flue Pipe 12 305 mm Ceiling to Furnace 24 610 mm Floor 0 0 mm Installation Requirements 1 The Empyre Elite must be installed on a level sta...

Страница 12: ...ontrol box follow these instructions to re install the switch trigger remove the control front plate to view the inside of the control box guide the switch trigger into the slot next to the limit swit...

Страница 13: ...m Low Water Temperature Protection It is the Responsibility of the installer to provide low water temperature protection in the design of the heat distribution system The Empyre Elite furnace is no di...

Страница 14: ...s recommended that a line be installed between the overflow port and suitable catch pan or drain 1 Hook up supply to Supply port and return to Return port as indicated see page 8 2 Install shut off va...

Страница 15: ...eeds and will conform to all local codes The Pro Fab Industries warranty covers the Empyre Elite furnace only and does not include anything outside of the Empyre Elite furnace Pro Fab Industries takes...

Страница 16: ...rm as low as possible PUMP BALL VALVE THERMOMETER BOILER DRAIN TEMPERING OR MIXING VALVE SYMBOLS INDEX Side Arm Installation To domestic heating system Hot water in from Empyre Elite furnace To top of...

Страница 17: ...door Furnace runs out of wood Figure 1 Note The existing furnace functions as a standby The aquastat on the standby furnace should be turned lower than the aquastat on the Empyre Elite Auxiliary Heat...

Страница 18: ...ow Check water level again 8 Add Pro Fab approved water treatment through vent opening Figure 1 9 Check water level when water temperature is 170 F 77 C and add water until level indicator shows full...

Страница 19: ...n burning extremely dry firewood pieces should be over 5 12 7 cm in diameter If using high moisture wood use pieces that are less than 5 12 7 cm in diameter It is good to mix the dry and wet wood when...

Страница 20: ...out of the firebox gently rake it into the secondary burn chamber through the opening in the bottom of the firebox It is important to rake ash buildup away from the back wall of the firebox 1 Do this...

Страница 21: ...vate by moving the lever fully to the right and then back to the left 3 Close door securely and move lever fully to the right Note if the lever is not fully to the right the buzzer will remain on and...

Страница 22: ...at exchanger flues weekly A buildup in the flues and chimney will cause a poor draft and reduce efficiency 6 Check and clean the air passages in the upper loading door frame several times during the h...

Страница 23: ...the water reservoir is full during the non heating season to prevent corrosion inside the water jacket 8 Add the correct amount as indicated on water treatment bottle of Pro Fab approved water treatm...

Страница 24: ...rcuit probe error Open probe error DTS Technical Data Accuracy 1 Output 16 Amp 1HP 240 Vac SPDT relay Supply voltage 115 Vac 10 Display 3 digit red DTS Programming Press SET SP text will appear on the...

Страница 25: ...23 Reference CAUTION DO NOT CONNECT THE ELECTRICAL COMPONENTS OF THIS UNIT TO ANY OTHER ELECTRICAL APPLIANCE DO NOT modify the electrical components or any other part of this furnace Modification to a...

Страница 26: ...Persist 1 Check if furnace is being operated properly 2 Remove flapper unit check to ensure the flap seals in the closed position clean and oil How to Remove and Reinstall 1 Disconnect power 2 Remove...

Страница 27: ...el type and quality For overall unit dimensions see Figure 1 Model 100 on page 26 Model 200 on page 27 For brick layout see Figure 2 Model 100 on page 26 Model 200 on page 27 For refractory layout see...

Страница 28: ...on Manual Reference Model 100 3 1 4 1 2 Not shown 0 817753 Revisions DESCRIPTION ECO Production Release 2535 REV 3 1 4 1 2 Not shown 817753 Figure 2 Brick Layout Figure 3 Refractory Layout Figure 1 Un...

Страница 29: ...PRODUCTION IN PART OR AS A WHOLE WITHOUT THE WRITTEN PERMISSION OF IS PROHIBITED PRINT DATE 10 05 11 CHECKED DRAWN DATE NAME DO NOT SCALE DRAWING Material Spec MATERIAL DWG NO SCALE 1 20 Pro Fab Indus...

Страница 30: ...air passage in the firebox floor is blocked by charcoal ash Using the ash rake always stir the firebox charcoal ash into the lower ash chamber before adding wood Limit the charcoal ash buildup and let...

Страница 31: ......

Страница 32: ...ranty Registration and a copy of the original bill invoice must be forwarded to Pro Fab within thirty 30 days of the date of purchase to validate the warranty Issue Date February 2013 Part No 817941R0...

Отзывы: