6. Inspection, maintenance and desludging
Premier Tech
25 / 64
Solido SMART
DOKK5110E 15.04.2020
6.3 Half-yearly maintenance
General maintenance (legally required)
Have maintenance performed on the wastewater treatment plant
by a specialist company
on a half-yearly basis
. The following work is to be performed and recorded in the
operations logbook
:
•
Inspection of the
operations logbook
and determination of regular operation
(target/actual comparison).
•
Function check of the important plant components (mechanical, electrical-technical, other),
checking in particular for the formation of bubbles and the pumping function of the air
lifters
•
Function check of the control unit and the alarm function
•
Maintenance of the compressor
•
Optimisation of the operation parameters on the basis of inspection results from the SBR
and outflow, if necessary in consultation with Premier Tech.
Warning:
Disconnect the wastewater treatment plant from the power supply before you
continue with the measures described below.
•
Check whether the functions of the calmed inlet, aeration devices, and clearwater lifter are
impacted by damaging substances. Substances that are damaging to functions should be
removed each time that maintenance is performed.
•
Check the volume of sludge and have the sludge removed by the operator if necessary.
Information about measuring sludge volume and desludging
see next chapter!
•
General cleaning maintenance, e.g. removal of sediment deposits
•
Inspection of the structural condition of the plant
•
Checking that aeration and deaeration is sufficient
•
Checking the concentration of oxygen in the SBR basin (SBR reactor)
•
Entering the maintenance results in the
operations logbook
Содержание Solido SMART
Страница 49: ...8 S40 control unit and available settings Premier Tech 49 64 Solido SMART DOKK5110E 15 04 2020...
Страница 56: ...9 Operational failures and resolving them Premier Tech 56 64 Solido SMART DOKK5110E 15 04 2020 NOTES...
Страница 60: ...10 Appendix Premier Tech 60 64 Solido SMART DOKK5110E 15 04 2020 10 4 EC declaration of conformity...