PREMAS® 4.0 Installation and Commissioning Manual
Page 38 / 44
4.3
Commissioning
IoT Box commissioning
1.
Check the voltage at the terminals of the breaker -F301 for 230VAC respectively 110VAC
2.
Switch on the breaker -F301; the system components are starting up.
3.
Check the status LEDs of the components and record the result:
Component
Label
LED
Expected
color
Actual LED
color
Power supply
-G301
PWR
Green
AI module,
Busworks XT
4.
-A811
STATUS
Yellow
RUN
Green
SIMATIC IOT2000
-A801
PWR
Green
STAT
Green
flashing
USER 1
Green*
USER 2
Green*
* it may take up to 4 minutes for theLED to change from RED to GREEN
Table 10: Status check of component LEDs
If the expected LED status has been confirmed, the system is ready for usage.
To use the system online, please connect to the PREMAS® Portal and select your machine for
access to the machine dashboard.