4.2.4
Installation of the product
4.2.4.1
Overview of the most important installation steps
Installation of temperature sensor at the head and boot
Installation of elongation measurement at the tension station
Laying signal cables from the sensors to the IoT Box
Laying signal cables from the I/O terminals of the plant control system to the IoT Box
Preparing the signals in the plant control system to interface with IoT Box
Installation of the IoT Box and antenna
4.2.4.2
Required tools
Following tools are required for installation.
The list may be extended depending on the local situation and needs.
•
For mechanical work
-
Folding yardstick, caliper, marker pen
-
Drill bit for metal and drilling machine
-
Angle grinder with cut-off wheel for metal
-
Power cord extension
-
Metal file/rasp
-
Welding equipment
-
Paint and paintbrush
-
Spanner/wrench set
-
Plus additional tools depending on local situation
•
For electrical work
-
Insulated screwdriver for electrical work
-
Wire cutter
-
Wire stripper
-
Multimeter
-
Plus additional tools depending on local situation
•
General
-
Scaffolding for access to mounting locations
Note: it is strongly recommended to have a fix installation to access the
measurement points and tension axle of the bucket elevator.