4.  Each a chain take-up bolt to one end of drive chain, using a #41 connecting link (See Fig. 5). 
5.  Insert chain take-up bolt in slot of bracket furthest away from operator. Secure location with 3/8 inch 

nuts, washers, and lock washers (See Fig. 5) 

6.  Disengage power drive unit with manual disconnect chain (See Fig 7). 
7.  Stretch drive chain out to operator and thread it around the first idler sprocket, and main drive sprocket, 

and second idler sprocket (See Figs 3 & 6). 

8.  Pull drive chain though to opposite end of gate, cut to correct length, and secure to gate bracket, using 

3/8 inch chain take-up bolt, as done in steps 4 and 5. 
Note: When pulling drive chain through operator, watch limit nuts on electric plate, to be sure they are 
not being mechanically driven through their normal end position. 

9.  Position chain take-up bolts in gate brackets, at each end of gate, so chain aligns with drive sprockets 

(See Fig. 2). 

10. Adjust chain tension using chain take-up bolts and outside nuts (See Fig. 5). 
11. When desired tension is achieved lock position with inside nuts (See Fig. 5). 
12. Replace chain guard. 

Содержание RSG 2000

Страница 1: ...herewith X Class II Commercial General Access Vehicular Gate Operator A vehicular gate operator or system intended for use in a commercial location or building such as a multifamily housing unit five...

Страница 2: ...er to ensure that the total system is safe for its intended use All secondary entrapment safety devices must be U L recognized to complete the operating system SYSTEM DESIGNER SAFETY INSTRUCTIONS 1 Fa...

Страница 3: ...the automatic controls do not work Locate the push button or key switch and small warning placard within sight of gate in a secured area at least 10 feet or more from the gate and fence to keep users...

Страница 4: ...e sure roller guards have been purchased and installed 7 Your gate system is required to have a primary and a secondary entrapment safety system installed and maintained See page 7 8 8 If your gate cl...

Страница 5: ...caught between the grille and the fence post or fence The potential hazard must be guarded It can be simply done by placing a screen mesh on the gate and fence in the area of the gate The screen must...

Страница 6: ...d cementing of mounting posts minimum of 2 deep 3 Set mounting posts and electrical conduits in place 4 Pour cement to secure mounting posts and let cure for two days prior to operator installation No...

Страница 7: ...ocket See Figs 3 6 8 Pull drive chain though to opposite end of gate cut to correct length and secure to gate bracket using 3 8 inch chain take up bolt as done in steps 4 and 5 Note When pulling drive...

Страница 8: ...ntacts must be NORMALLY OPEN Connect STOP button to terminal 4 Connect COMMON button to terminal 5 Connect OPEN button to terminal 6 Connect CLOSE to terminal 7 PRIMARY OBSTRUCTION SENSING DEVICE Note...

Страница 9: ...te Install photoelectric cell as close to inside of gate as possible Note Photo cells should be installed across gate opening and behind gate See Fig 11 at least 10 inches above ground 1 After sensors...

Страница 10: ...adio s installation manual to determine which wires are for the normally open contacts and which require the 24 VAC power supply TIMER TO CLOSE The operator is equipped with a timer to close option fo...

Страница 11: ...wrong turn off main power and recheck drive chain installation See Fig 4 6 If drive chain is correct consult the factory WARNING UNDER NO CIRCUMSTANCES SHOULD CONTROL STATION WIRING BE ALTERED IF ROTA...

Страница 12: ...ENTRY Open only 1 Connect MO to terminal 3 2 Connect common to terminal 5 DO NOT Connect N O to terminal 6 FIG 6 EXIT LOOP Open only 1 Connect common yellow to terminal 3 2 Connect N O blue to termina...