5 Start-up Operation
5.1 Start-up
Before beginning start-up the wiring of the Controller including all field devices must be completely terminated!
After switching the power supply “ON” and the end of the Power On Time, then the Controller is ready for use.
The electrochemical sensor needs a warm up time of 1 hour to reach its highest accuracy.
The Controller is delivered with standard parameters and stages/set points. The assignment of the relays to the
individual stages can occur at start-up unless arrangements have been made with the factory for programming. All
other parameters are to be examined and adapted to the local conditions.